Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
28
matching recommendationsSIC | 2679 | Converted Paper Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0434 # 08 Y:2017 | 08 | 2017 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,523 | $40,000 | Not Implemented |
LE0434 # 07 Y:2017 | 07 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $483 | $1,450 | Implemented |
LE0434 # 06 Y:2017 | 06 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,129 | $5,350 | Not Implemented |
LE0434 # 05 Y:2017 | 05 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,921 | $65,000 | Not Implemented |
LE0434 # 04 Y:2017 | 04 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $576 | $300 | Not Implemented |
LE0434 # 03 Y:2017 | 03 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,560 | $1,080 | Implemented |
LE0434 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,031 | $1,000 | Not Implemented |
LE0434 # 01 Y:2017 | 01 | 2017 | INSTALL TIMERS AND/OR THERMOSTATS | $1,784 | $28 | Implemented |
LE0404 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,623 | $1,000 | Implemented |
LE0404 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,130 | $6,092 | Implemented |
LE0404 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,569 | $36,281 | Implemented |
LE0404 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,793 | $17,019 | Implemented |
LE0404 # 04 Y:2015 | 04 | 2015 | INSTALL OCCUPANCY SENSORS | $92 | $240 | Not Implemented |
LE0404 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $7,827 | $4,800 | Implemented |
LE0404 # 01 Y:2015 | 01 | 2015 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,045 | $276 | Not Implemented |
LE0316 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,608 | $67,275 | Not Implemented |
LE0316 # 13 Y:2011 | 13 | 2011 | INSTALL SKYLIGHTS | $1,030 | $22,500 | Not Implemented |
LE0316 # 12 Y:2011 | 12 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,182 | $1,000 | Not Implemented |
LE0316 # 11 Y:2011 | 11 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,567 | $3,205 | Not Implemented |
LE0316 # 10 Y:2011 | 10 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,860 | $3,600 | Not Implemented |
LE0316 # 09 Y:2011 | 09 | 2011 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,438 | $23,800 | Not Implemented |
LE0316 # 08 Y:2011 | 08 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,621 | $1,120 | Not Implemented |
LE0316 # 07 Y:2011 | 07 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,209 | $3,200 | Not Implemented |
LE0316 # 06 Y:2011 | 06 | 2011 | INSTALL OCCUPANCY SENSORS | $2,639 | $2,250 | Not Implemented |
LE0316 # 05 Y:2011 | 05 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,230 | $25,000 | Not Implemented |