Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
141
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0615 # 07 Y:2024 | 07 | 2024 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $8,021 | $5,898 | n/a |
UF0615 # 02 Y:2024 | 02 | 2024 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $66,500 | $73,000 | n/a |
UF0615 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $81,057 | $322,608 | n/a |
UF0615 # 11 Y:2024 | 11 | 2024 | IMPROVE SPACE COMFORT CONDITIONING | $20,106 | $3,020 | n/a |
UF0615 # 10 Y:2024 | 10 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $4,769 | $2,352 | n/a |
UF0615 # 03 Y:2024 | 03 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $41,878 | $24,095 | n/a |
UF0615 # 09 Y:2024 | 09 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $2,456 | $4,000 | n/a |
UF0615 # 08 Y:2024 | 08 | 2024 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,975 | $10,830 | n/a |
UF0615 # 04 Y:2024 | 04 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $14,133 | $22,755 | n/a |
UF0615 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,078 | $355 | n/a |
UF0615 # 05 Y:2024 | 05 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,911 | $816 | n/a |
LE0567 # 01 Y:2024 | 01 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $1,055 | $600 | n/a |
LE0567 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $226 | $1,056 | n/a |
LE0567 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $8,772 | $43,016 | n/a |
LE0567 # 04 Y:2024 | 04 | 2024 | INSTALL OCCUPANCY SENSORS | $892 | $1,500 | n/a |
LE0567 # 03 Y:2024 | 03 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,776 | $9,000 | n/a |
LE0567 # 02 Y:2024 | 02 | 2024 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $54,396 | $50,000 | n/a |
TT0312 # 01 Y:2024 | 01 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $36,945 | $0 | n/a |
TT0312 # 03 Y:2024 | 03 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $30,815 | $6,360 | n/a |
TT0312 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,292 | $635 | n/a |
TT0312 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,740 | $11,250 | n/a |
TT0312 # 06 Y:2024 | 06 | 2024 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $14,000 | $12,000 | n/a |
TT0312 # 09 Y:2024 | 09 | 2024 | INSTALL OCCUPANCY SENSORS | $1,294 | $1,860 | n/a |
TT0312 # 10 Y:2024 | 10 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,155 | $4,810 | n/a |
TT0312 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,728 | $30 | n/a |