Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
317
matching recommendationsSIC | 3273 | Ready-mixed Concrete |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0088 # 03 Y:1983 | 03 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $309 | $312 | Not Implemented |
KU0088 # 04 Y:1983 | 04 | 1983 | INSTALL AUTOMATIC STACK DAMPER | $111 | $300 | Not Implemented |
KU0088 # 05 Y:1983 | 05 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $63 | $60 | Not Implemented |
OK0060 # 01 Y:1982 | 01 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $406 | $294 | Not Implemented |
OK0060 # 02 Y:1982 | 02 | 1982 | INSTALL TIMERS AND/OR THERMOSTATS | $436 | $600 | Implemented |
OK0060 # 03 Y:1982 | 03 | 1982 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $293 | $0 | Not Implemented |
OK0060 # 04 Y:1982 | 04 | 1982 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $31,428 | $18,000 | Not Implemented |
OK0060 # 05 Y:1982 | 05 | 1982 | INSULATE BARE EQUIPMENT | $3,052 | $5,840 | Not Implemented |
OK0060 # 06 Y:1982 | 06 | 1982 | INSULATE BARE EQUIPMENT | $497 | $202 | Not Implemented |
OK0060 # 07 Y:1982 | 07 | 1982 | INSULATE BARE EQUIPMENT | $438 | $254 | Not Implemented |
OK0060 # 08 Y:1982 | 08 | 1982 | INSULATE BARE EQUIPMENT | $4,281 | $2,495 | Not Implemented |
UD0044 # 01 Y:1982 | 01 | 1982 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $4,962 | $2,000 | Not Implemented |
KU0038 # 01 Y:1982 | 01 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,385 | $2,427 | Not Implemented |
KU0038 # 02 Y:1982 | 02 | 1982 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $810 | $335 | Not Implemented |
KU0038 # 03 Y:1982 | 03 | 1982 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $495 | $0 | Not Implemented |
KU0038 # 04 Y:1982 | 04 | 1982 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $300 | $400 | Not Implemented |
KU0038 # 05 Y:1982 | 05 | 1982 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $190 | $200 | Not Implemented |