IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

77

matching recommendations
Reset
SIC 332 Iron And Steel Foundries
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0432 # 12 Y:2008 12 2008 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $2,480 $5,333 Implemented
IA0432 # 07 Y:2008 07 2008 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $423 $143 Implemented
IA0432 # 06 Y:2008 06 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $416 $322 Implemented
IA0432 # 05 Y:2008 05 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $979 $17 Implemented
IA0432 # 11 Y:2008 11 2008 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $2,042 $930 Not Implemented
IA0432 # 04 Y:2008 04 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $986 $67 Not Implemented
IA0432 # 03 Y:2008 03 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,859 $620 Implemented
IA0432 # 02 Y:2008 02 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,099 $1,884 Implemented
IA0432 # 01 Y:2008 01 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $687 $330 Implemented
IA0432 # 08 Y:2008 08 2008 RECOVER WASTE HEAT FROM EQUIPMENT $16,295 $3,442 Not Implemented
IA0432 # 09 Y:2008 09 2008 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $571 $1,650 Implemented
IA0432 # 10 Y:2008 10 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,529 $1,781 Not Implemented
IA0331 # 05 Y:2003 05 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $614 $586 Implemented
IA0331 # 01 Y:2003 01 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $11,482 $915 Implemented
IA0331 # 02 Y:2003 02 2003 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $7,583 $1,994 Not Implemented
IA0331 # 03 Y:2003 03 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $5,790 $5,790 Not Implemented
IA0331 # 04 Y:2003 04 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,662 $3,125 Implemented
IA0331 # 09 Y:2003 09 2003 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $34,789 $29,757 Not Implemented
IA0331 # 14 Y:2003 14 2003 COVER OPEN TANKS $1,451 $4,500 Not Implemented
IA0331 # 07 Y:2003 07 2003 INSTALL OCCUPANCY SENSORS $203 $599 Implemented
IA0331 # 11 Y:2003 11 2003 INSULATE BARE EQUIPMENT $1,491 $3,352 Not Implemented
IA0331 # 13 Y:2003 13 2003 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $18,530 $12,000 Not Implemented
IA0331 # 08 Y:2003 08 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,450 $1,754 Implemented
IA0331 # 10 Y:2003 10 2003 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $8,977 $10,800 Not Implemented
IA0331 # 12 Y:2003 12 2003 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $200,000 $200,000 Not Implemented