Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,208
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0038 # 05 Y:1994 | 05 | 1994 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $705 | $1,624 | Not Implemented |
NC0038 # 06 Y:1994 | 06 | 1994 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $11,775 | $7,000 | Implemented |
NC0038 # 07 Y:1994 | 07 | 1994 | INSULATE BARE EQUIPMENT | $9,420 | $1,500 | Implemented |
NC0038 # 08 Y:1994 | 08 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,154 | $2,128 | Implemented |
NC0039 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,241 | $2,018 | Implemented |
NC0039 # 02 Y:1994 | 02 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,052 | $3,850 | Not Implemented |
NC0039 # 03 Y:1994 | 03 | 1994 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $1,432 | $1,500 | Not Implemented |
NC0039 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,710 | $600 | Not Implemented |
NC0039 # 05 Y:1994 | 05 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,600 | $420 | Not Implemented |
NC0039 # 06 Y:1994 | 06 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,307 | $2,500 | Not Implemented |
NC0039 # 07 Y:1994 | 07 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,306 | $5,070 | Not Implemented |
NC0039 # 08 Y:1994 | 08 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $156 | $570 | Not Implemented |
NC0039 # 09 Y:1994 | 09 | 1994 | USE POWER DURING OFF-PEAK PERIODS | $8,928 | $0 | Implemented |
NC0039 # 10 Y:1994 | 10 | 1994 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $18,760 | $16,000 | Not Implemented |
NC0039 # 11 Y:1994 | 11 | 1994 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,900 | $500 | Not Implemented |
AR0043 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,278 | $1,074 | Implemented |
AR0043 # 02 Y:1994 | 02 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,070 | $540 | Implemented |
AR0043 # 03 Y:1994 | 03 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,361 | $350 | Implemented |
AR0043 # 04 Y:1994 | 04 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $12,100 | $1,000 | Implemented |
IA0094 # 01 Y:1994 | 01 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,255 | $315 | Implemented |
IA0094 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,502 | $1,430 | Implemented |
IA0094 # 03 Y:1994 | 03 | 1994 | INSTALL OCCUPANCY SENSORS | $2,191 | $1,224 | Not Implemented |
IA0094 # 04 Y:1994 | 04 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,523 | $10,378 | Implemented |
IA0094 # 05 Y:1994 | 05 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,916 | $390 | Not Implemented |
IA0094 # 06 Y:1994 | 06 | 1994 | INSULATE BARE EQUIPMENT | $184 | $68 | Not Implemented |