IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

40

matching recommendations
Reset
SIC 3449 Miscellaneous Metal Work
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TA0120 # 04 Y:2006 04 2006 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $24,151 $0 Not Implemented
AM0117 # 05 Y:1991 05 1991 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $75 $5,858 Not Implemented
AM0117 # 01 Y:1991 01 1991 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $4,016 $0 Not Implemented
AM0117 # 02 Y:1991 02 1991 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $945 $5,640 Not Implemented
AM0117 # 03 Y:1991 03 1991 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $330 $340 Not Implemented
AM0117 # 04 Y:1991 04 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $93 $100 Not Implemented
AM0059 # 05 Y:1989 05 1989 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $325 $0 Implemented
AM0059 # 06 Y:1989 06 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $62 $15 Implemented
AM0059 # 07 Y:1989 07 1989 IMPROVE LUBRICATION PRACTICES $227 $0 Not Implemented
AM0059 # 08 Y:1989 08 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $166 $340 Implemented
AM0059 # 09 Y:1989 09 1989 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $110 $0 Implemented
AM0059 # 04 Y:1989 04 1989 RECOVER WASTE HEAT FROM EQUIPMENT $495 $1,000 Not Implemented
AM0059 # 03 Y:1989 03 1989 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS $845 $840 Not Implemented
AM0059 # 02 Y:1989 02 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,382 $300 Implemented
AM0059 # 01 Y:1989 01 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,105 $2,176 Implemented