IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

8

matching recommendations
Reset
SIC 3511 Turbines And Turbine Generator Sets
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0103 # 01 Y:1990 01 1990 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $25,900 $0 Implemented
AM0103 # 02 Y:1990 02 1990 OPTIMIZE PLANT POWER FACTOR $18,300 $28,390 Implemented
AM0103 # 03 Y:1990 03 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,810 $9,500 Implemented
AM0103 # 04 Y:1990 04 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,895 $990 Implemented
AM0103 # 05 Y:1990 05 1990 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,480 $0 Implemented
AM0103 # 06 Y:1990 06 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $944 $0 Implemented
AM0103 # 07 Y:1990 07 1990 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $674 $160 Implemented
AM0103 # 08 Y:1990 08 1990 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $490 $268 Implemented