Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
23
matching recommendationsSIC | 353 | Construction And Related Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0219 # 09 Y:2019 | 09 | 2019 | APPLY FOR INVESTMENT INCENTIVES | $1,440 | $0 | Implemented |
TT0219 # 08 Y:2019 | 08 | 2019 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $5,757 | $16,291 | Implemented |
TT0219 # 03 Y:2019 | 03 | 2019 | USE OPTIMUM THICKNESS INSULATION | $27,754 | $105,000 | Implemented |
TT0219 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $50,161 | $360 | Implemented |
TT0219 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $53,170 | $61,967 | Implemented |
TT0075 # 08 Y:2011 | 08 | 2011 | ISOLATE HOT OR COLD EQUIPMENT | $1,379 | $2,500 | Implemented |
TT0075 # 07 Y:2011 | 07 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,771 | $1,152 | Implemented |
TT0075 # 06 Y:2011 | 06 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,146 | $5,000 | Implemented |
TT0075 # 05 Y:2011 | 05 | 2011 | INSTALL COMMON HEADER ON COMPRESSORS | $44,869 | $32,200 | Implemented |
TT0075 # 04 Y:2011 | 04 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,202 | $14,000 | Implemented |
TT0075 # 03 Y:2011 | 03 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $47,625 | $21,000 | Implemented |
TN0515 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,397 | $600 | Implemented |
TN0515 # 03 Y:1994 | 03 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,662 | $0 | Implemented |
TN0515 # 02 Y:1994 | 02 | 1994 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,074 | $1,300 | Implemented |
TN0483 # 01 Y:1993 | 01 | 1993 | INSULATE BARE EQUIPMENT | $2,932 | $175 | Implemented |
TN0356 # 06 Y:1988 | 06 | 1988 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $752 | $150 | Implemented |
TN0356 # 05 Y:1988 | 05 | 1988 | IMPROVE LUBRICATION PRACTICES | $1,370 | $1,200 | Implemented |
TN0356 # 04 Y:1988 | 04 | 1988 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $2,846 | $6,850 | Implemented |
TN0356 # 03 Y:1988 | 03 | 1988 | KEEP LAMPS AND REFLECTORS CLEAN | $12,279 | $14,384 | Implemented |
TN0356 # 02 Y:1988 | 02 | 1988 | INSTALL TIMERS AND/OR THERMOSTATS | $9,024 | $8,980 | Implemented |
TN0356 # 01 Y:1988 | 01 | 1988 | USE RADIANT HEATER FOR SPOT HEATING | $17,070 | $34,560 | Implemented |
TN0240 # 01 Y:1985 | 01 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,237 | $180 | Implemented |
TN0240 # 03 Y:1985 | 03 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $2,349 | $300 | Implemented |