Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

126

matching recommendations
Reset
SIC 353 Construction And Related Machinery
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0273 # 06 Y:1996 06 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,466 $486 Implemented
WI0273 # 07 Y:1996 07 1996 INSTALL OCCUPANCY SENSORS $446 $300 Not Implemented
WI0273 # 08 Y:1996 08 1996 INSTALL TIMERS AND/OR THERMOSTATS $959 $400 Not Implemented
WI0273 # 09 Y:1996 09 1996 COVER CONTAINERS TO MINIMIZE EVAPORATIVE LOSSES $928 $1,000 Not Implemented
WI0273 # 10 Y:1996 10 1996 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $657 $740 Implemented
WI0273 # 11 Y:1996 11 1996 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $451 $0 Not Implemented
WI0273 # 12 Y:1996 12 1996 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $144 $585 Implemented
WI0195 # 01 Y:1993 01 1993 OPTIMIZE PLANT POWER FACTOR $21,307 $17,400 Implemented
WI0195 # 02 Y:1993 02 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,291 $3,946 Not Implemented
WI0195 # 03 Y:1993 03 1993 INSTALL OCCUPANCY SENSORS $247 $150 Not Implemented
WI0195 # 04 Y:1993 04 1993 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,037 $1,050 Not Implemented
WI0195 # 05 Y:1993 05 1993 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $859 $0 Not Implemented
WI0195 # 06 Y:1993 06 1993 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $206 $350 Not Implemented
WI0195 # 07 Y:1993 07 1993 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $671 $0 Implemented
WI0195 # 08 Y:1993 08 1993 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $384 $588 Not Implemented
WI0195 # 09 Y:1993 09 1993 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $132 $0 Not Implemented
WI0195 # 10 Y:1993 10 1993 INSULATE BARE EQUIPMENT $187 $660 Not Implemented
WI0045 # 01 Y:1988 01 1988 IMPROVE LUBRICATION PRACTICES $3,520 $0 Implemented
WI0045 # 02 Y:1988 02 1988 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $842 $0 Implemented
WI0045 # 03 Y:1988 03 1988 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $114 $89 Implemented
WI0045 # 04 Y:1988 04 1988 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $1,605 $2,500 Not Implemented
WI0045 # 05 Y:1988 05 1988 USE DEMAND CONTROLLER OR LOAD SHEDDER $3,144 $5,000 Implemented
WI0030 # 01 Y:1988 01 1988 IMPROVE LUBRICATION PRACTICES $2,541 $0 Not Implemented
WI0030 # 02 Y:1988 02 1988 RECOVER WASTE HEAT FROM EQUIPMENT $3,548 $1,400 Implemented
WI0030 # 03 Y:1988 03 1988 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $184 $468 Implemented