IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

714

matching recommendations
Reset
SIC 3533 Oil And Gas Field Machinery
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1024 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,608 $4,500 Not Implemented
OK1024 # 04 Y:2020 04 2020 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $515 $540 Not Implemented
OK1024 # 05 Y:2020 05 2020 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $1,437 $3,178 Not Implemented
OK1024 # 06 Y:2020 06 2020 INSTALL TIMERS AND/OR THERMOSTATS $34,324 $2,448 Not Implemented
OK1007 # 01 Y:2019 01 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,929 $3,017 Not Implemented
OK1007 # 02 Y:2019 02 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $390 $1,047 Not Implemented
OK1007 # 03 Y:2019 03 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $9,238 $0 Not Implemented
OK1007 # 04 Y:2019 04 2019 OPTIMIZE PLANT POWER FACTOR $2,995 $1,980 Not Implemented
OK1007 # 05 Y:2019 05 2019 INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM $96,866 $35,244 Not Implemented
LS1901 # 06 Y:2019 06 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,246 $21,652 Not Implemented
LS1901 # 05 Y:2019 05 2019 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $45,500 $27,000 Not Implemented
LS1901 # 04 Y:2019 04 2019 IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS $1,150 $100 Implemented
LS1901 # 03 Y:2019 03 2019 INSTALL OCCUPANCY SENSORS $483 $75 Not Implemented
LS1901 # 02 Y:2019 02 2019 INSTALL OCCUPANCY SENSORS $1,421 $50 Implemented
LS1901 # 01 Y:2019 01 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $374 $25 Not Implemented
AM0760 # 06 Y:2018 06 2018 USE PHOTOCELL CONTROLS $823 $963 Implemented
AM0760 # 05 Y:2018 05 2018 INSTALL OCCUPANCY SENSORS $1,121 $2,000 Not Implemented
AM0760 # 04 Y:2018 04 2018 PAY UTILITY BILLS ON TIME $1,351 $0 Implemented
AM0760 # 03 Y:2018 03 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,298 $1,000 Implemented
AM0760 # 02 Y:2018 02 2018 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $13,500 $300 Implemented
AM0760 # 01 Y:2018 01 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,161 $43,708 Implemented
AM0759 # 01 Y:2018 01 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,939 $12,678 Not Implemented
AM0759 # 02 Y:2018 02 2018 OPTIMIZE PLANT POWER FACTOR $5,714 $12,461 Not Implemented
AM0759 # 03 Y:2018 03 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,305 $100 Implemented
AM0759 # 04 Y:2018 04 2018 PAY UTILITY BILLS ON TIME $2,702 $100 Implemented