Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
714
matching recommendationsSIC | 3533 | Oil And Gas Field Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1024 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,608 | $4,500 | Not Implemented |
OK1024 # 04 Y:2020 | 04 | 2020 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $515 | $540 | Not Implemented |
OK1024 # 05 Y:2020 | 05 | 2020 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,437 | $3,178 | Not Implemented |
OK1024 # 06 Y:2020 | 06 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $34,324 | $2,448 | Not Implemented |
OK1007 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,929 | $3,017 | Not Implemented |
OK1007 # 02 Y:2019 | 02 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $390 | $1,047 | Not Implemented |
OK1007 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,238 | $0 | Not Implemented |
OK1007 # 04 Y:2019 | 04 | 2019 | OPTIMIZE PLANT POWER FACTOR | $2,995 | $1,980 | Not Implemented |
OK1007 # 05 Y:2019 | 05 | 2019 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $96,866 | $35,244 | Not Implemented |
LS1901 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,246 | $21,652 | Not Implemented |
LS1901 # 05 Y:2019 | 05 | 2019 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $45,500 | $27,000 | Not Implemented |
LS1901 # 04 Y:2019 | 04 | 2019 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $1,150 | $100 | Implemented |
LS1901 # 03 Y:2019 | 03 | 2019 | INSTALL OCCUPANCY SENSORS | $483 | $75 | Not Implemented |
LS1901 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $1,421 | $50 | Implemented |
LS1901 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $374 | $25 | Not Implemented |
AM0760 # 06 Y:2018 | 06 | 2018 | USE PHOTOCELL CONTROLS | $823 | $963 | Implemented |
AM0760 # 05 Y:2018 | 05 | 2018 | INSTALL OCCUPANCY SENSORS | $1,121 | $2,000 | Not Implemented |
AM0760 # 04 Y:2018 | 04 | 2018 | PAY UTILITY BILLS ON TIME | $1,351 | $0 | Implemented |
AM0760 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,298 | $1,000 | Implemented |
AM0760 # 02 Y:2018 | 02 | 2018 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $13,500 | $300 | Implemented |
AM0760 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,161 | $43,708 | Implemented |
AM0759 # 08 Y:2018 | 08 | 2018 | INSTALL OCCUPANCY SENSORS | $383 | $585 | Not Implemented |
AM0759 # 07 Y:2018 | 07 | 2018 | USE SYNTHETIC LUBRICANT | $231 | $100 | Implemented |
AM0759 # 06 Y:2018 | 06 | 2018 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,207 | $100 | Implemented |
AM0759 # 05 Y:2018 | 05 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,676 | $700 | Not Implemented |