Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsSIC | 3533 | Oil And Gas Field Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0811 # 06 Y:2020 | 06 | 2020 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $460 | $200 | Implemented |
AM0811 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,530 | $255 | Implemented |
AM0811 # 04 Y:2020 | 04 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,900 | $60 | Not Implemented |
AM0811 # 03 Y:2020 | 03 | 2020 | PAY UTILITY BILLS ON TIME | $7,866 | $0 | Implemented |
AM0811 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,800 | $6,000 | Implemented |
AM0811 # 01 Y:2020 | 01 | 2020 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $19,123 | $20,000 | Implemented |
AM0809 # 02 Y:2020 | 02 | 2020 | OPTIMIZE PLANT POWER FACTOR | $39,500 | $80,400 | Not Implemented |
AM0809 # 09 Y:2020 | 09 | 2020 | INSTALL SPECTRAL REFLECTORS / DELAMP | $856 | $1,020 | Implemented |
AM0809 # 08 Y:2020 | 08 | 2020 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $620 | $34 | Implemented |
AM0809 # 07 Y:2020 | 07 | 2020 | INSTALL OCCUPANCY SENSORS | $737 | $474 | Not Implemented |
AM0809 # 06 Y:2020 | 06 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $847 | $2,360 | Implemented |
AM0809 # 05 Y:2020 | 05 | 2020 | PAY UTILITY BILLS ON TIME | $3,380 | $0 | Implemented |
AM0809 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,060 | $13,360 | Not Implemented |
AM0809 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,340 | $60,200 | Implemented |
AM0809 # 01 Y:2020 | 01 | 2020 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $103,240 | $20,000 | Implemented |
OK1024 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,729 | $0 | Not Implemented |
OK1024 # 02 Y:2020 | 02 | 2020 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,084 | $2,187 | Not Implemented |
OK1024 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,608 | $4,500 | Not Implemented |
OK1024 # 04 Y:2020 | 04 | 2020 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $515 | $540 | Not Implemented |
OK1024 # 05 Y:2020 | 05 | 2020 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,437 | $3,178 | Not Implemented |
OK1024 # 06 Y:2020 | 06 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $34,324 | $2,448 | Not Implemented |