IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

45

matching recommendations
Reset
SIC 363 Household Appliances
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MO0021 # 07 Y:1991 07 1991 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,114 $435 Implemented
MO0021 # 06 Y:1991 06 1991 INSULATE BARE EQUIPMENT $1,577 $4,250 Implemented
MO0021 # 05 Y:1991 05 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $961 $0 Implemented
MO0021 # 04 Y:1991 04 1991 INSULATE BARE EQUIPMENT $3,394 $6,952 Implemented
MO0021 # 03 Y:1991 03 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,061 $5,968 Implemented
MO0021 # 02 Y:1991 02 1991 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,790 $1,316 Implemented
MO0021 # 01 Y:1991 01 1991 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,969 $1,195 Implemented
MO0018 # 04 Y:1991 04 1991 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,232 $315 Implemented
MO0018 # 01 Y:1991 01 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,073 $542 Implemented
MO0018 # 02 Y:1991 02 1991 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $2,564 $1,000 Implemented
MO0018 # 03 Y:1991 03 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $426 $757 Implemented
MO0018 # 05 Y:1991 05 1991 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $469 $700 Implemented
KU0190 # 01 Y:1986 01 1986 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE $3,383 $50 Implemented
KU0190 # 08 Y:1986 08 1986 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $207 $0 Implemented
KU0190 # 07 Y:1986 07 1986 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $249 $50 Implemented
KU0190 # 06 Y:1986 06 1986 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $673 $10 Implemented
KU0190 # 05 Y:1986 05 1986 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $658 $120 Implemented
KU0190 # 04 Y:1986 04 1986 IMPROVE LUBRICATION PRACTICES $1,009 $600 Not Implemented
KU0190 # 03 Y:1986 03 1986 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,038 $1,510 Implemented
KU0190 # 02 Y:1986 02 1986 USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS $215 $0 Implemented