ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0426 # 03 Y:2013 | 03 | 2013 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $8,403 | $649 | Not Implemented |
SF0426 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,301 | $7,526 | Not Implemented |
SF0426 # 05 Y:2013 | 05 | 2013 | INSTALL OCCUPANCY SENSORS | $373 | $1,619 | Not Implemented |
SF0426 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,979 | $17,191 | Implemented |
UK1213 # 12 Y:2012 | 12 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,563 | $4,550 | Implemented |
UK1213 # 01 Y:2012 | 01 | 2012 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $16,324 | $0 | Implemented |
UK1213 # 02 Y:2012 | 02 | 2012 | OPTIMIZE PLANT POWER FACTOR | $14,754 | $11,220 | Not Implemented |
UK1213 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,410 | $26,824 | Implemented |
UK1213 # 04 Y:2012 | 04 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $4,375 | $10,500 | Not Implemented |
UK1213 # 05 Y:2012 | 05 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $460 | $756 | Not Implemented |
UK1213 # 06 Y:2012 | 06 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $350 | $500 | Not Implemented |
UK1213 # 07 Y:2012 | 07 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $343 | $269 | Implemented |
UK1213 # 11 Y:2012 | 11 | 2012 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $3,482 | $988 | Not Implemented |
UK1213 # 10 Y:2012 | 10 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $49,180 | $6,650 | Not Implemented |
UK1213 # 08 Y:2012 | 08 | 2012 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $654 | $337 | Implemented |
UK1213 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $316 | $327 | Not Implemented |
MZ0091 # 01 Y:2012 | 01 | 2012 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $190,000 | $5,000 | Implemented |
MZ0091 # 02 Y:2012 | 02 | 2012 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $18,699 | $0 | Implemented |
MZ0091 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $30,809 | $27,800 | Implemented |
MZ0091 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,504 | $0 | Implemented |
MZ0091 # 05 Y:2012 | 05 | 2012 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $3,133 | $0 | Implemented |
MZ0091 # 06 Y:2012 | 06 | 2012 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $24,311 | $9,516 | Implemented |
SU0159 # 04 Y:2003 | 04 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,171 | $0 | Implemented |
SU0159 # 05 Y:2003 | 05 | 2003 | REPLACE BOILER | $1,148 | $13,507 | Implemented |
SU0159 # 07 Y:2003 | 07 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $276 | $523 | Implemented |