Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,374
matching recommendationsSIC | 371 | Motor Vehicles And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0315 # 03 Y:1987 | 03 | 1987 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $5,598 | $3,000 | Implemented |
TN0315 # 04 Y:1987 | 04 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,370 | $375 | Implemented |
TN0315 # 05 Y:1987 | 05 | 1987 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,491 | $0 | Not Implemented |
TN0315 # 06 Y:1987 | 06 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,568 | $280 | Implemented |
TN0315 # 07 Y:1987 | 07 | 1987 | USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD | $1,202 | $2,800 | Not Implemented |
TN0315 # 08 Y:1987 | 08 | 1987 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $894 | $1,776 | Not Implemented |
GT0325 # 01 Y:1987 | 01 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,220 | $100 | Not Implemented |
GT0325 # 02 Y:1987 | 02 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $226 | $300 | Implemented |
GT0325 # 03 Y:1987 | 03 | 1987 | IMPROVE LUBRICATION PRACTICES | $1,410 | $0 | Not Implemented |
GT0325 # 04 Y:1987 | 04 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,100 | $7,200 | Not Implemented |
GT0325 # 05 Y:1987 | 05 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $387 | $321 | Not Implemented |
GT0325 # 06 Y:1987 | 06 | 1987 | INSTALL SET-BACK TIMERS | $290 | $200 | Not Implemented |
GT0327 # 01 Y:1987 | 01 | 1987 | INSTALL SET-BACK TIMERS | $180 | $100 | Not Implemented |
GT0327 # 02 Y:1987 | 02 | 1987 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $32,320 | $25,000 | Implemented |
GT0327 # 03 Y:1987 | 03 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,115 | $812 | Implemented |
GT0327 # 04 Y:1987 | 04 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,406 | $3,500 | Implemented |
GT0327 # 05 Y:1987 | 05 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,690 | $4,300 | Not Implemented |
GT0327 # 06 Y:1987 | 06 | 1987 | REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF | $15,020 | $54,424 | Not Implemented |
AT0082 # 01 Y:1987 | 01 | 1987 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $17,889 | $30,000 | Not Implemented |
AT0082 # 02 Y:1987 | 02 | 1987 | RECOVER WASTE HEAT FROM EQUIPMENT | $587 | $1,500 | Implemented |
AT0082 # 03 Y:1987 | 03 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $111 | $0 | Implemented |
AT0082 # 04 Y:1987 | 04 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $97 | $173 | Implemented |
AT0082 # 05 Y:1987 | 05 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $205 | $0 | Implemented |
AM0004 # 01 Y:1987 | 01 | 1987 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,995 | $0 | Implemented |
AM0004 # 02 Y:1987 | 02 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $151 | $107 | Implemented |