Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
798
matching recommendationsSIC | 373 | Ship And Boat Building And Repairing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0063 # 11 Y:1993 | 11 | 1993 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,659 | $2,850 | Not Implemented |
UF0063 # 12 Y:1993 | 12 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $1,081 | $1,300 | Not Implemented |
UF0063 # 13 Y:1993 | 13 | 1993 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,265 | $0 | Not Implemented |
UF0063 # 14 Y:1993 | 14 | 1993 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $1,560 | $1,400 | Not Implemented |
UF0063 # 15 Y:1993 | 15 | 1993 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $61,821 | $250,000 | Not Implemented |
AM0161 # 01 Y:1992 | 01 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,600 | $630 | Implemented |
AM0161 # 02 Y:1992 | 02 | 1992 | REDUCE LOAD ON ELECTRICAL CONDUCTOR TO REDUCE HEATING LOSSES | $4,700 | $2,255 | Not Implemented |
AM0161 # 03 Y:1992 | 03 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,855 | $0 | Implemented |
AM0161 # 04 Y:1992 | 04 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,290 | $985 | Implemented |
AM0161 # 05 Y:1992 | 05 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,420 | $0 | Implemented |
AM0161 # 06 Y:1992 | 06 | 1992 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,205 | $5,050 | Not Implemented |
AM0161 # 07 Y:1992 | 07 | 1992 | TURN OFF EQUIPMENT WHEN NOT IN USE | $690 | $0 | Implemented |
AM0161 # 08 Y:1992 | 08 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $280 | $450 | Implemented |
AM0162 # 01 Y:1992 | 01 | 1992 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,720 | $782 | Implemented |
AM0162 # 02 Y:1992 | 02 | 1992 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $1,150 | $5,746 | Implemented |
AM0162 # 03 Y:1992 | 03 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,010 | $300 | Implemented |
AM0162 # 04 Y:1992 | 04 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $700 | $215 | Implemented |
UF0041 # 01 Y:1992 | 01 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,221 | $798 | Implemented |
UF0041 # 02 Y:1992 | 02 | 1992 | INSTALL SPECTRAL REFLECTORS / DELAMP | $4,215 | $11,940 | Not Implemented |
UF0041 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $182 | $1,863 | Not Implemented |
UF0041 # 04 Y:1992 | 04 | 1992 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $400 | $1,200 | Implemented |
UF0041 # 05 Y:1992 | 05 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $775 | $7,950 | Implemented |
UF0041 # 06 Y:1992 | 06 | 1992 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $125 | $660 | Implemented |
UF0041 # 07 Y:1992 | 07 | 1992 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,204 | $4,750 | Not Implemented |
UF0041 # 08 Y:1992 | 08 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $583 | $0 | Not Implemented |