Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsSIC | 3829 | Measuring & Controlling Devices, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0088 # 02 Y:1994 | 02 | 1994 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,722 | $200 | Implemented |
SD0088 # 03 Y:1994 | 03 | 1994 | INSULATE BARE EQUIPMENT | $376 | $235 | Implemented |
SD0088 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,853 | $150 | Implemented |
SD0088 # 05 Y:1994 | 05 | 1994 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $117,014 | $245,000 | Implemented |
SD0088 # 06 Y:1994 | 06 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $40,436 | $95,019 | Implemented |
SD0088 # 07 Y:1994 | 07 | 1994 | INSTALL SPECTRAL REFLECTORS / DELAMP | $39,115 | $43,220 | Implemented |
SD0088 # 08 Y:1994 | 08 | 1994 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $4,548 | $810 | Implemented |
SD0088 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,963 | $4,300 | Implemented |
WV0029 # 12 Y:1994 | 12 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $995 | $260 | Implemented |
WV0029 # 11 Y:1994 | 11 | 1994 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $227 | $0 | Implemented |
WV0029 # 10 Y:1994 | 10 | 1994 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $207 | $0 | Implemented |
WV0029 # 09 Y:1994 | 09 | 1994 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $11,134 | $4,830 | Not Implemented |
WV0029 # 08 Y:1994 | 08 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $216 | $303 | Implemented |
WV0029 # 07 Y:1994 | 07 | 1994 | INSTALL / REPAIR INSULATION ON STEAM LINES | $192 | $15 | Implemented |
WV0029 # 06 Y:1994 | 06 | 1994 | INSULATE BARE EQUIPMENT | $12,889 | $3,360 | Not Implemented |
WV0029 # 05 Y:1994 | 05 | 1994 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $4,413 | $340 | Not Implemented |
WV0029 # 04 Y:1994 | 04 | 1994 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $279 | $0 | Implemented |
WV0029 # 03 Y:1994 | 03 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $475 | $300 | Implemented |
WV0029 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $461 | $14,040 | Not Implemented |
WV0029 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,087 | $1,173 | Implemented |