IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

8

matching recommendations
Reset
SIC 594 Miscellaneous Shopping Goods Stores
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MUCM01 # 01 Y:2022 01 2022 USE OPTIMUM TEMPERATURE $16,827 $0 Implemented
MUCM01 # 02 Y:2022 02 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $32,030 $3,319 Implemented
MUCM01 # 03 Y:2022 03 2022 INSTALL OCCUPANCY SENSORS $697 $731 Not Implemented
MUCM01 # 04 Y:2022 04 2022 USE PHOTOCELL CONTROLS $305 $507 Not Implemented
MUCM01 # 05 Y:2022 05 2022 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS $530 $62 Implemented
MUCM01 # 06 Y:2022 06 2022 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $816 $410 Not Implemented
MUCM01 # 07 Y:2022 07 2022 INSTALL / REPAIR INSULATION ON STEAM LINES $188 $81 Not Implemented
MUCM01 # 08 Y:2022 08 2022 RESCHEDULE AND REARRANGE MULTIPLE-SOURCE HEATING SYSTEMS $749 $130 Not Implemented