Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsSIC | 799 | Misc. Amusement, Recreation Services |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ1001 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $507 | $1,000 | n/a |
MZ1001 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $904 | $770 | n/a |
MZ1001 # 04 Y:2023 | 04 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $10,268 | $2,010 | n/a |
MZ1001 # 01 Y:2023 | 01 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $12,758 | $83,955 | n/a |
OK1101 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,284 | $18,000 | Not Implemented |
OK1101 # 03 Y:2023 | 03 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $2,746 | $1,530 | Not Implemented |
OK1101 # 02 Y:2023 | 02 | 2023 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $5,367 | $34,835 | Not Implemented |
OK1101 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,452 | $2,800 | Implemented |
OK1100 # 01 Y:2023 | 01 | 2023 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $1,078 | $1,122 | Not Implemented |
OK1100 # 02 Y:2023 | 02 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $392 | $1,586 | Not Implemented |
OK1100 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,157 | $3,000 | Not Implemented |
OK1100 # 04 Y:2023 | 04 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $19,727 | $187,200 | Not Implemented |
LS1123 # 01 Y:2023 | 01 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $2,082 | $150 | Implemented |
LS1123 # 02 Y:2023 | 02 | 2023 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,809 | $300 | Implemented |
LS1123 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,349 | $1,730 | Implemented |
LS1123 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $79 | $75 | Implemented |
LS1123 # 05 Y:2023 | 05 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $2,321 | $2,881 | Implemented |
LS0223 # 05 Y:2023 | 05 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $200 | $630 | Not Implemented |
LS0223 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,193 | $2,990 | Implemented |
LS0223 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $39 | $50 | Implemented |
LS0223 # 02 Y:2023 | 02 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $160 | $50 | Implemented |
LS0223 # 01 Y:2023 | 01 | 2023 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $11,364 | $1,800 | Not Implemented |