Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
143,603
matching recommendationsARC | 2. | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0315 # 07 Y:2024 | 07 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,015 | $15,600 | n/a |
TT0315 # 08 Y:2024 | 08 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,159 | $1,700 | n/a |
TT0315 # 09 Y:2024 | 09 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $204 | $184 | n/a |
GT0975 # 01 Y:2024 | 01 | 2024 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $442 | $197 | n/a |
GT0975 # 02 Y:2024 | 02 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,668 | $2,732 | n/a |
GT0975 # 03 Y:2024 | 03 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,280 | $1,334 | n/a |
GT0975 # 04 Y:2024 | 04 | 2024 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $39,992 | $87,500 | n/a |
GT0975 # 05 Y:2024 | 05 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $770 | $1,850 | n/a |
GT0975 # 06 Y:2024 | 06 | 2024 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $4,603 | $11,665 | n/a |
LS0524 # 01 Y:2024 | 01 | 2024 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $5,077 | $2,040 | n/a |
LS0524 # 02 Y:2024 | 02 | 2024 | INSTALL OCCUPANCY SENSORS | $340 | $200 | n/a |
LS0524 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $620 | $578 | n/a |
OK1110 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $52,945 | $56,850 | n/a |
OK1110 # 02 Y:2024 | 02 | 2024 | INSTALL OCCUPANCY SENSORS | $3,264 | $1,330 | n/a |
OK1110 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $5,873 | $7,892 | n/a |
OK1110 # 04 Y:2024 | 04 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $30,588 | $280,800 | n/a |
OK1110 # 05 Y:2024 | 05 | 2024 | OPERATE BOILERS ON HIGH FIRE SETTING | $8,594 | $22,000 | n/a |
OK1110 # 06 Y:2024 | 06 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $15,219 | $12,400 | n/a |
OK1110 # 07 Y:2024 | 07 | 2024 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $2,681 | $1,861 | n/a |
OK1110 # 08 Y:2024 | 08 | 2024 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $996 | $160 | n/a |
OR0786 # 01 Y:2024 | 01 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,491 | $0 | n/a |
OR0786 # 02 Y:2024 | 02 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,522 | $2,500 | n/a |
OR0786 # 03 Y:2024 | 03 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,567 | $726 | n/a |
OR0786 # 04 Y:2024 | 04 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $7,048 | $108,930 | n/a |
OR0787 # 01 Y:2024 | 01 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $13,182 | $130,619 | n/a |