Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,128
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0629 # 01 Y:2025 | 01 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,502 | $0 | n/a |
SF0629 # 03 Y:2025 | 03 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,560 | $254 | n/a |
SF0629 # 04 Y:2025 | 04 | 2025 | INSULATE BARE EQUIPMENT | $6,353 | $4,013 | n/a |
SF0629 # 05 Y:2025 | 05 | 2025 | INSTALL OCCUPANCY SENSORS | $2,585 | $8,372 | n/a |
SF0629 # 06 Y:2025 | 06 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,343 | $22,807 | n/a |
SF0629 # 07 Y:2025 | 07 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $121,562 | $882,352 | n/a |
SF0628 # 03 Y:2025 | 03 | 2025 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $1,061 | $6,460 | Implemented |
SF0628 # 02 Y:2025 | 02 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,482 | $770 | Implemented |
SF0628 # 01 Y:2025 | 01 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $72,544 | $0 | Implemented |
SF0625 # 02 Y:2024 | 02 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $8,680 | $588 | n/a |
SF0625 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,669 | $0 | n/a |
SF0625 # 03 Y:2024 | 03 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $8,671 | $516 | n/a |
SF0625 # 04 Y:2024 | 04 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,071 | $854 | n/a |
SF0625 # 05 Y:2024 | 05 | 2024 | INCREASE AMOUNT OF CONDENSATE RETURNED | $26,010 | $8,735 | n/a |
SF0625 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,576 | $3,859 | n/a |
SF0625 # 08 Y:2024 | 08 | 2024 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $155,547 | $160,389 | n/a |
SF0625 # 09 Y:2024 | 09 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $14,307 | $15,295 | n/a |
SF0625 # 10 Y:2024 | 10 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,369 | $7,928 | n/a |
SF0625 # 11 Y:2024 | 11 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $177,385 | $2,104,448 | n/a |
SF0625 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,943 | $10,277 | n/a |
SF0624 # 05 Y:2024 | 05 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $130,070 | $760,719 | Implemented |
SF0624 # 04 Y:2024 | 04 | 2024 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $14,370 | $58,959 | Not Implemented |
SF0624 # 03 Y:2024 | 03 | 2024 | USE PHOTOCELL CONTROLS | $509 | $718 | Not Implemented |
SF0624 # 02 Y:2024 | 02 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,414 | $1,073 | Implemented |
SF0624 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,603 | $0 | Implemented |