Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,799
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0433 # 09 Y:2010 | 09 | 2010 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $23,836 | $4,000 | Not Implemented |
UF0433 # 10 Y:2010 | 10 | 2010 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $1,885 | $816 | Implemented |
UF0432 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $33,739 | $32,047 | Not Implemented |
UF0432 # 02 Y:2010 | 02 | 2010 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $4,188 | $5,591 | Not Implemented |
UF0432 # 03 Y:2010 | 03 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $14,940 | $2,240 | Not Implemented |
UF0432 # 04 Y:2010 | 04 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,539 | $719 | Not Implemented |
UF0432 # 05 Y:2010 | 05 | 2010 | USE PHOTOCELL CONTROLS | $6,416 | $768 | Not Implemented |
UF0432 # 06 Y:2010 | 06 | 2010 | INSTALL COMMON HEADER ON COMPRESSORS | $1,520 | $0 | Not Implemented |
UF0432 # 07 Y:2010 | 07 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,000 | $2,700 | Not Implemented |
UF0432 # 08 Y:2010 | 08 | 2010 | DEVELOP A REPAIR/REPLACE POLICY | $364 | $0 | Not Implemented |
UF0432 # 09 Y:2010 | 09 | 2010 | CLEAN CONDENSER TUBES | $1,343 | $120 | Not Implemented |
UF0432 # 10 Y:2010 | 10 | 2010 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $3,120 | $0 | Not Implemented |
UF0432 # 11 Y:2010 | 11 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,637 | $1,500 | Not Implemented |
UF0431 # 01 Y:2010 | 01 | 2010 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,250 | $0 | Not Implemented |
UF0431 # 02 Y:2010 | 02 | 2010 | INSTALL SKYLIGHTS | $1,303 | $4,408 | Not Implemented |
UF0431 # 03 Y:2010 | 03 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,351 | $39,918 | Not Implemented |
UF0431 # 04 Y:2010 | 04 | 2010 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $6,300 | $0 | Not Implemented |
UF0431 # 05 Y:2010 | 05 | 2010 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $5,063 | $1,050 | Not Implemented |
UF0431 # 06 Y:2010 | 06 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,297 | $449 | Not Implemented |
UF0431 # 07 Y:2010 | 07 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $808 | $0 | Not Implemented |
UF0431 # 08 Y:2010 | 08 | 2010 | UPGRADE CONTROLS ON COMPRESSORS | $1,346 | $0 | Not Implemented |
UF0431 # 09 Y:2010 | 09 | 2010 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $1,815 | $0 | Not Implemented |
UF0430 # 01 Y:2010 | 01 | 2010 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $28,959 | $5,655 | Implemented |
UF0430 # 02 Y:2010 | 02 | 2010 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,044 | $0 | Implemented |
UF0430 # 03 Y:2010 | 03 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,531 | $0 | Not Implemented |