Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,474
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0094 # 06 Y:1994 | 06 | 1994 | USE PHOTOCELL CONTROLS | $2,113 | $2,400 | Not Implemented |
UF0094 # 07 Y:1994 | 07 | 1994 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $6,412 | $18,200 | Not Implemented |
UF0094 # 08 Y:1994 | 08 | 1994 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $961 | $0 | Not Implemented |
UF0094 # 09 Y:1994 | 09 | 1994 | LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION | $1,520 | $3,200 | Not Implemented |
UF0094 # 10 Y:1994 | 10 | 1994 | REDUCE GLAZED AREAS IN BUILDINGS | $1,516 | $300 | Not Implemented |
NC0029 # 01 Y:1994 | 01 | 1994 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $11,457 | $153,000 | Not Implemented |
NC0029 # 02 Y:1994 | 02 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,131 | $480 | Implemented |
NC0029 # 03 Y:1994 | 03 | 1994 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $14,345 | $40,000 | Implemented |
NC0029 # 04 Y:1994 | 04 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,050 | $520 | Not Implemented |
NC0029 # 05 Y:1994 | 05 | 1994 | INSULATE BARE EQUIPMENT | $562 | $378 | Not Implemented |
NC0028 # 01 Y:1994 | 01 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $153 | $250 | Implemented |
NC0028 # 02 Y:1994 | 02 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,218 | $600 | Implemented |
NC0028 # 03 Y:1994 | 03 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $787 | $240 | Not Implemented |
NC0028 # 04 Y:1994 | 04 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $736 | $1,510 | Implemented |
NC0028 # 05 Y:1994 | 05 | 1994 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $7,525 | $7,000 | Not Implemented |
KU0430 # 01 Y:1994 | 01 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $24,083 | $25,905 | Not Implemented |
KU0430 # 02 Y:1994 | 02 | 1994 | USE SOLAR HEAT TO HEAT WATER | $380 | $400 | Not Implemented |
KU0430 # 03 Y:1994 | 03 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $321 | $334 | Not Implemented |
KU0430 # 04 Y:1994 | 04 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $292 | $1,088 | Implemented |
KU0430 # 05 Y:1994 | 05 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $161 | $0 | Implemented |
KU0430 # 06 Y:1994 | 06 | 1994 | INSTALL SKYLIGHTS | $5,873 | $14,300 | Not Implemented |
KU0430 # 07 Y:1994 | 07 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,683 | $20,936 | Not Implemented |
KU0430 # 08 Y:1994 | 08 | 1994 | INSTALL OCCUPANCY SENSORS | $1,505 | $700 | Not Implemented |
KU0430 # 09 Y:1994 | 09 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $429 | $544 | Not Implemented |
WV0037 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $536 | $214 | Implemented |