Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,682
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0063 # 02 Y:1993 | 02 | 1993 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $5,451 | $3,230 | Not Implemented |
IA0063 # 03 Y:1993 | 03 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,186 | $100 | Implemented |
IA0063 # 04 Y:1993 | 04 | 1993 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $2,421 | $685 | Implemented |
IA0063 # 05 Y:1993 | 05 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $402 | $925 | Implemented |
IA0063 # 06 Y:1993 | 06 | 1993 | USE RADIANT HEATER FOR SPOT HEATING | $2,719 | $10,200 | Implemented |
IA0063 # 07 Y:1993 | 07 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $165 | $0 | Not Implemented |
IA0063 # 08 Y:1993 | 08 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $528 | $840 | Not Implemented |
IA0063 # 09 Y:1993 | 09 | 1993 | INSTALL OCCUPANCY SENSORS | $473 | $665 | Implemented |
IA0063 # 10 Y:1993 | 10 | 1993 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $556 | $215 | Implemented |
IA0063 # 11 Y:1993 | 11 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $595 | $1,350 | Implemented |
WI0187 # 01 Y:1993 | 01 | 1993 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $2,534 | $750 | Implemented |
WI0187 # 02 Y:1993 | 02 | 1993 | INSULATE BARE EQUIPMENT | $343 | $184 | Implemented |
WI0187 # 03 Y:1993 | 03 | 1993 | INSULATE BARE EQUIPMENT | $278 | $40 | Implemented |
WI0187 # 04 Y:1993 | 04 | 1993 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,097 | $200 | Not Implemented |
WI0187 # 05 Y:1993 | 05 | 1993 | UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM | $2,023 | $5,000 | Not Implemented |
WI0187 # 06 Y:1993 | 06 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $841 | $2,800 | Not Implemented |
WI0187 # 07 Y:1993 | 07 | 1993 | INSTALL OCCUPANCY SENSORS | $167 | $150 | Not Implemented |
WI0187 # 08 Y:1993 | 08 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $387 | $120 | Implemented |
WI0187 # 09 Y:1993 | 09 | 1993 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $255 | $600 | Not Implemented |
WI0187 # 10 Y:1993 | 10 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $217 | $0 | Not Implemented |
WI0186 # 01 Y:1993 | 01 | 1993 | UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM | $14,209 | $15,000 | n/a |
WI0186 # 02 Y:1993 | 02 | 1993 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $12,375 | $0 | n/a |
WI0186 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,035 | $10,375 | n/a |
WI0186 # 04 Y:1993 | 04 | 1993 | USE PHOTOCELL CONTROLS | $1,100 | $525 | n/a |
WI0186 # 05 Y:1993 | 05 | 1993 | INSTALL OCCUPANCY SENSORS | $211 | $372 | n/a |