Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,821
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0653 # 14 Y:2023 | 14 | 2023 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,320 | $1,500 | Implemented |
WV0653 # 15 Y:2023 | 15 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,200 | $3,036 | Implemented |
WV0653 # 16 Y:2023 | 16 | 2023 | INSULATE BARE EQUIPMENT | $1,621 | $787 | Implemented |
WV0653 # 17 Y:2023 | 17 | 2023 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $1,453 | $7,240 | Not Implemented |
LS2316 # 01 Y:2023 | 01 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $3,030 | $30 | Not Implemented |
LS2316 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,894 | $135 | Implemented |
LS2316 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $33,726 | $4,515 | Implemented |
LS2316 # 04 Y:2023 | 04 | 2023 | USE PHOTOCELL CONTROLS | $1,069 | $370 | Not Implemented |
LS2316 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $47,296 | $25,200 | Not Implemented |
LS2316 # 06 Y:2023 | 06 | 2023 | INSTALL OCCUPANCY SENSORS | $460 | $753 | Implemented |
MI0428 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $18,313 | $3,360 | Implemented |
MI0428 # 02 Y:2023 | 02 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,381 | $120 | Not Implemented |
MI0428 # 03 Y:2023 | 03 | 2023 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $8,729 | $0 | Implemented |
MI0428 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,867 | $1,660 | Implemented |
MI0428 # 05 Y:2023 | 05 | 2023 | AIR CONDITION ONLY SPACE NECESSARY | $3,598 | $6,724 | Not Implemented |
MI0428 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,014 | $960 | Implemented |
MI0428 # 07 Y:2023 | 07 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,528 | $3,130 | Not Implemented |
MI0428 # 08 Y:2023 | 08 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,396 | $2,834 | Implemented |
MI0428 # 09 Y:2023 | 09 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $1,230 | $40 | Implemented |
MI0428 # 10 Y:2023 | 10 | 2023 | INSTALL OCCUPANCY SENSORS | $1,117 | $816 | Implemented |
MI0428 # 11 Y:2023 | 11 | 2023 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $898 | $98 | Implemented |
CI0022 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $30,795 | $185,422 | n/a |
CI0022 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $18,385 | $60,000 | n/a |
CI0022 # 03 Y:2023 | 03 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $17,839 | $9,000 | n/a |
CI0022 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,948 | $300 | n/a |