Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,263
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LT8387 # 01 Y:2023 | 01 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,856 | $0 | n/a |
LS2405 # 01 Y:2024 | 01 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,278 | $0 | Implemented |
LS2405 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,023 | $50 | Not Implemented |
LS2405 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,417 | $135 | Implemented |
LS2405 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44,207 | $25,301 | Implemented |
LS2405 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $155,225 | $550,000 | Implemented |
LS2405 # 06 Y:2024 | 06 | 2024 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $129,015 | $600,000 | Not Implemented |
LS0224 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,796 | $25 | Implemented |
LS0224 # 02 Y:2024 | 02 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $1,962 | $75 | Implemented |
LS0224 # 03 Y:2024 | 03 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,495 | $20,000 | Not Implemented |
LS0224 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,104 | $1,413 | Implemented |
LS0224 # 05 Y:2024 | 05 | 2024 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $175,678 | $600,000 | Implemented |
LS0224 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $12,486 | $113,400 | Not Implemented |
LS0224 # 07 Y:2024 | 07 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $38,021 | $514,800 | Not Implemented |
LS2404 # 01 Y:2024 | 01 | 2024 | INSTALL OCCUPANCY SENSORS | $5,988 | $275 | Implemented |
LS2404 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,008 | $75 | Not Implemented |
LS2404 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,054 | $135 | Implemented |
LS2404 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,771 | $3,080 | Implemented |
LS2404 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,458 | $11,138 | Implemented |
LS2403 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,116 | $25 | Not Implemented |
LS2403 # 02 Y:2024 | 02 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $1,928 | $25 | Implemented |
LS2403 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,306 | $3,600 | Implemented |
LS2403 # 04 Y:2024 | 04 | 2024 | DO NOT USE COMPRESSED AIR FOR PERSONAL COOLING | $1,205 | $950 | Implemented |
LS2402 # 01 Y:2024 | 01 | 2024 | PAY BILLS ON TIME TO AVOID LATE FEES | $35,595 | $0 | Implemented |
LS2402 # 02 Y:2024 | 02 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $8,573 | $125 | Implemented |