IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,091

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0340 # 02 Y:1991 02 1991 RECOVER WASTE HEAT FROM EQUIPMENT $2,573 $232 Not Implemented
OK0340 # 03 Y:1991 03 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $207 $169 Not Implemented
OK0340 # 04 Y:1991 04 1991 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $683 $0 Not Implemented
OK0342 # 01 Y:1991 01 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,190 $276 Implemented
OK0342 # 02 Y:1991 02 1991 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $445 $0 Implemented
OK0342 # 03 Y:1991 03 1991 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,397 $0 Implemented
OK0342 # 04 Y:1991 04 1991 INSTALL TIMERS AND/OR THERMOSTATS $10,794 $6,200 Implemented
OK0342 # 05 Y:1991 05 1991 RECOVER WASTE HEAT FROM EQUIPMENT $2,644 $3,510 Implemented
OK0342 # 06 Y:1991 06 1991 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $896 $2,600 Implemented
UD0341 # 01 Y:1991 01 1991 INSTALL SET-BACK TIMERS $494 $0 Not Implemented
UD0341 # 02 Y:1991 02 1991 INSTALL TIMERS AND/OR THERMOSTATS $2,837 $20,000 Not Implemented
UD0341 # 03 Y:1991 03 1991 INSTALL TIMERS AND/OR THERMOSTATS $442 $20,000 Not Implemented
UD0342 # 01 Y:1991 01 1991 OPTIMIZE PLANT POWER FACTOR $9,819 $0 Not Implemented
UD0342 # 02 Y:1991 02 1991 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,238 $0 Not Implemented
UD0342 # 03 Y:1991 03 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,746 $0 Not Implemented
UD0342 # 04 Y:1991 04 1991 USE COOLING AIR WHICH COOLS HOT WORK PIECES FOR SPACE HEATING $1,611 $2,000 Not Implemented
UD0342 # 05 Y:1991 05 1991 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $3,474 $11,865 Not Implemented
UD0343 # 01 Y:1991 01 1991 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $801 $100 Not Implemented
UD0343 # 02 Y:1991 02 1991 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $1,695 $0 Not Implemented
UD0343 # 03 Y:1991 03 1991 INSTALL SET-BACK TIMERS $1,735 $0 Not Implemented
UD0343 # 04 Y:1991 04 1991 INSTALL STORM WINDOWS AND DOORS $1,587 $1,100 Not Implemented
UD0343 # 05 Y:1991 05 1991 MINIMIZE WATER USAGE $2,314 $0 Not Implemented
UF0002 # 01 Y:1991 01 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,788 $2,118 Implemented
UF0002 # 02 Y:1991 02 1991 KEEP LAMPS AND REFLECTORS CLEAN $9,472 $3,600 Implemented
UF0002 # 03 Y:1991 03 1991 INSTALL SET-BACK TIMERS $3,111 $288 Implemented