Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,737
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0162 # 04 Y:2020 | 04 | 2020 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $328 | $1,141 | Implemented |
IC0234 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,669 | $32,097 | Implemented |
IC0234 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,418 | $1,107 | Implemented |
IC0234 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,059 | $3,380 | Implemented |
IC0234 # 04 Y:2020 | 04 | 2020 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,075 | $3,800 | Implemented |
LS2004 # 01 Y:2020 | 01 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $2,617 | $0 | Implemented |
LS2004 # 02 Y:2020 | 02 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,091 | $25 | Not Implemented |
LS2004 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,899 | $0 | Implemented |
LS2004 # 04 Y:2020 | 04 | 2020 | INSTALL OCCUPANCY SENSORS | $10,389 | $3,245 | Not Implemented |
LS2004 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,227 | $0 | Implemented |
MA0812 # 01 Y:2020 | 01 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $228,815 | $892,794 | Not Implemented |
MA0812 # 02 Y:2020 | 02 | 2020 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $56,847 | $3,250 | Not Implemented |
MA0812 # 03 Y:2020 | 03 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $35,615 | $32,940 | Implemented |
MA0812 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,190 | $5,960 | Implemented |
MA0812 # 05 Y:2020 | 05 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,774 | $16,650 | Implemented |
MA0812 # 06 Y:2020 | 06 | 2020 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $8,604 | $500 | Not Implemented |
AS0479 # 01 Y:2020 | 01 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $20,215 | $200 | Implemented |
AS0479 # 02 Y:2020 | 02 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $15,892 | $111,826 | Not Implemented |
AS0479 # 03 Y:2020 | 03 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,108 | $6,016 | Implemented |
AS0479 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,979 | $1,639 | Implemented |
AS0479 # 05 Y:2020 | 05 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,834 | $330 | Implemented |
AS0479 # 06 Y:2020 | 06 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,794 | $7,400 | Implemented |
AS0479 # 07 Y:2020 | 07 | 2020 | INSTALL OCCUPANCY SENSORS | $1,596 | $4,600 | Not Implemented |
AS0479 # 08 Y:2020 | 08 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $60 | $281 | Not Implemented |
MA0813 # 01 Y:2020 | 01 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $60,067 | $253,810 | Not Implemented |