Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,130
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0055 # 11 Y:1993 | 11 | 1993 | INSTALL OCCUPANCY SENSORS | $601 | $1,050 | Not Implemented |
IA0055 # 12 Y:1993 | 12 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $430 | $189 | Not Implemented |
IA0055 # 13 Y:1993 | 13 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $195 | $300 | Not Implemented |
MO0088 # 01 Y:1993 | 01 | 1993 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $22,701 | $8,000 | Implemented |
MO0088 # 02 Y:1993 | 02 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,251 | $2,550 | Not Implemented |
MO0088 # 03 Y:1993 | 03 | 1993 | USE SYNTHETIC LUBRICANT | $2,068 | $1,920 | Not Implemented |
MO0088 # 04 Y:1993 | 04 | 1993 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,403 | $200 | Not Implemented |
MO0088 # 05 Y:1993 | 05 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,132 | $13,043 | Not Implemented |
MO0088 # 06 Y:1993 | 06 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,984 | $1,095 | Not Implemented |
MO0088 # 07 Y:1993 | 07 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,692 | $16,551 | Not Implemented |
MO0088 # 08 Y:1993 | 08 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,129 | $727 | Not Implemented |
MO0088 # 09 Y:1993 | 09 | 1993 | PAY UTILITY BILLS ON TIME | $985 | $0 | Implemented |
UF0069 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,381 | $1,705 | Implemented |
UF0069 # 02 Y:1993 | 02 | 1993 | INSTALL SPECTRAL REFLECTORS / DELAMP | $776 | $2,256 | Not Implemented |
UF0069 # 03 Y:1993 | 03 | 1993 | INSTALL OCCUPANCY SENSORS | $486 | $768 | Not Implemented |
UF0069 # 04 Y:1993 | 04 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,295 | $2,669 | Implemented |
UF0069 # 05 Y:1993 | 05 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,049 | $1,000 | Implemented |
UF0069 # 06 Y:1993 | 06 | 1993 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $16,058 | $0 | Implemented |
UF0073 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,136 | $215 | Not Implemented |
UF0073 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $383 | $1,267 | Not Implemented |
UF0073 # 03 Y:1993 | 03 | 1993 | DISCONNECT BALLASTS | $345 | $480 | Not Implemented |
UF0073 # 04 Y:1993 | 04 | 1993 | INSTALL OCCUPANCY SENSORS | $266 | $104 | Not Implemented |
UF0073 # 05 Y:1993 | 05 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,259 | $9,775 | Implemented |
UF0073 # 06 Y:1993 | 06 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,954 | $1,400 | Implemented |
UF0073 # 07 Y:1993 | 07 | 1993 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $78,000 | $24,600 | Not Implemented |