Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,377
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ST0014 # 08 Y:1985 | 08 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,305 | $200 | Implemented |
ST0014 # 09 Y:1985 | 09 | 1985 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $2,840 | $23 | Not Implemented |
ST0014 # 10 Y:1985 | 10 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $14,474 | $50 | Implemented |
ST0015 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,216 | $1,229 | Not Implemented |
ST0015 # 02 Y:1985 | 02 | 1985 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $828 | $0 | Implemented |
ST0015 # 03 Y:1985 | 03 | 1985 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $581 | $370 | Not Implemented |
ST0015 # 04 Y:1985 | 04 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $180 | $120 | Implemented |
ST0015 # 05 Y:1985 | 05 | 1985 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,280 | $500 | Implemented |
ST0015 # 06 Y:1985 | 06 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $4,844 | $1,000 | Implemented |
ST0015 # 07 Y:1985 | 07 | 1985 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $359 | $41 | Implemented |
ST0015 # 08 Y:1985 | 08 | 1985 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $6,985 | $1,900 | Not Implemented |
ST0016 # 01 Y:1985 | 01 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,538 | $136 | Implemented |
ST0016 # 02 Y:1985 | 02 | 1985 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $1,120 | $0 | Not Implemented |
ST0016 # 03 Y:1985 | 03 | 1985 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $939 | $700 | Implemented |
ST0016 # 04 Y:1985 | 04 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,817 | $1,597 | Implemented |
ST0016 # 05 Y:1985 | 05 | 1985 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $752 | $5,600 | Not Implemented |
ST0016 # 06 Y:1985 | 06 | 1985 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $13,005 | $0 | Implemented |
ST0016 # 07 Y:1985 | 07 | 1985 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,643 | $378 | Implemented |
ST0020 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,174 | $532 | Implemented |
ST0020 # 02 Y:1985 | 02 | 1985 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $101 | $0 | Implemented |
ST0020 # 03 Y:1985 | 03 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $581 | $537 | Implemented |
ST0020 # 04 Y:1985 | 04 | 1985 | INSTALL AUTOMATIC STACK DAMPER | $886 | $1,074 | Implemented |
ST0020 # 05 Y:1985 | 05 | 1985 | USE COMPRESSOR AIR FILTERS | $1,957 | $120 | Implemented |
ST0020 # 06 Y:1985 | 06 | 1985 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,756 | $1,900 | Implemented |
ST0020 # 07 Y:1985 | 07 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,620 | $64 | Implemented |