Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
83
matching recommendationsSIC | 267 | Misc. Converted Paper Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0147 # 04 Y:2002 | 04 | 2002 | INSTALL OCCUPANCY SENSORS | $450 | $104 | Not Implemented |
LL0147 # 03 Y:2002 | 03 | 2002 | USE PHOTOCELL CONTROLS | $2,355 | $421 | Implemented |
LL0147 # 05 Y:2002 | 05 | 2002 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $9,126 | $0 | Not Implemented |
LL0147 # 02 Y:2002 | 02 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,034 | $0 | Not Implemented |
LL0147 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,887 | $1,500 | Implemented |
LL0121 # 04 Y:2001 | 04 | 2001 | PAY UTILITY BILLS ON TIME | $3,665 | $0 | Implemented |
LL0121 # 01 Y:2001 | 01 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,365 | $2,160 | Implemented |
LL0121 # 05 Y:2001 | 05 | 2001 | PAY UTILITY BILLS ON TIME | $10,648 | $0 | Implemented |
LL0121 # 02 Y:2001 | 02 | 2001 | OPTIMIZE PLANT POWER FACTOR | $4,301 | $15,406 | Not Implemented |
LL0121 # 03 Y:2001 | 03 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $593 | $495 | Implemented |
LL0112 # 06 Y:2001 | 06 | 2001 | USE PHOTOCELL CONTROLS | $109,215 | $1,962 | Not Implemented |
LL0112 # 05 Y:2001 | 05 | 2001 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $353,891 | $50,860 | Implemented |
LL0112 # 04 Y:2001 | 04 | 2001 | INSULATE BARE EQUIPMENT | $5,437 | $9,810 | Implemented |
LL0112 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,154 | $1,200 | Implemented |
LL0112 # 02 Y:2001 | 02 | 2001 | BURN A LESS EXPENSIVE GRADE OF FUEL | $1,598,858 | $154,800 | Not Implemented |
LL0112 # 01 Y:2001 | 01 | 2001 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $477,641 | $1,116,799 | Not Implemented |
AR0059 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,115 | $554 | Implemented |
AR0059 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,258 | $3,820 | Implemented |
AR0059 # 02 Y:1995 | 02 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $13,187 | $3,130 | Implemented |
AR0059 # 04 Y:1995 | 04 | 1995 | OPTIMIZE PLANT POWER FACTOR | $2,940 | $7,020 | Not Implemented |
AR0059 # 05 Y:1995 | 05 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $623 | $0 | Implemented |
AR0059 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,288 | $200 | Implemented |
AR0059 # 07 Y:1995 | 07 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $996 | $300 | Implemented |
AR0059 # 08 Y:1995 | 08 | 1995 | INSULATE BARE EQUIPMENT | $7,225 | $210 | Not Implemented |
AR0050 # 01 Y:1995 | 01 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,999 | $400 | Implemented |