Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1989 |
Principal Product | POTATO & CORN CHIPS |
NAICS | n/a |
SIC | 2096 - Potato Chips And Similar Snacks |
Sales | $10,000,000-$50,000,000 |
# of Employees | 233 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 31,000,000 Pounds |
Production Hrs. Annual | 6,072 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $293,578 | 6,441,677 | kWh | $0.05 |
Natural Gas | $451,743 | 125,178 | MMBtu | $3.61 |
TOTAL ENERGY COSTS | $745,321 | |||
RECOMMENDED SAVINGS* | $62,543 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,593 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $30,343 Cost: $60,000 |
$(-8,506) | (-138,042) | $38,849 | 10,761 |
$(-8,506) (-138,042) kWh |
$38,849 10,761 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $14,450 Cost: $10,000 |
- | - | $14,450 | 4,002 |
- - kWh |
$14,450 4,002 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $7,260 Cost: $300 |
- | - | $7,260 | 2,010 |
- - kWh |
$7,260 2,010 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $3,080 Cost: $1,400 |
$3,080 | 50,703 | - | - |
$3,080 50,703 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,030 Cost: $303 |
$2,030 | 35,756 | - | - |
$2,030 35,756 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $2,005 Cost: $600 |
- | - | $2,005 | 555 |
- - kWh |
$2,005 555 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,490 Cost: $1,100 |
$1,490 | 31,067 | - | - |
$1,490 31,067 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,415 Cost: - |
$1,415 | 19,343 | - | - |
$1,415 19,343 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $470 Cost: $300 |
- | - | $470 | 130 |
- - kWh |
$470 130 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $62,543 Cost: $74,003 |
$(-491) | (-1,173) | $63,034 | 17,458 | $(-491) (-1,173) kWh |
$63,034 17,458 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,593 Cost: $63,400 |
$(-2,521) | (-36,929) | $48,114 | 13,326 | $(-2,521) (-36,929) kWh |
$48,114 13,326 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |