IAC Assessment: AM0189
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0189
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 1993
Principal Product Machining and welding metal products for oil and natural gas
NAICS n/a
SIC 3351 - Copper Rolling And Drawing
Sales $5,000,000-$10,000,000
# of Employees 100
Plant Area (Sq.Ft.) 100,100
Annual Production 1,500,000 Pounds
Production Hrs. Annual 5,221
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $91,160 1,152,989 kWh $0.08
Natural Gas $4,571 965 MMBtu $4.74
TOTAL ENERGY COSTS $95,731
RECOMMENDED SAVINGS* $28,150 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $19,140
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$11,300
Cost:
$1,500
$11,300 230,950 $11,300
230,950
kWh
02: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY Savings:
$8,740
Cost:
$26,200
$8,740 3,517 $8,740
3,517
kWh
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$4,540
Cost:
$70
$4,540 65,944 $4,540
65,944
kWh
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$2,760
Cost:
-
$2,760 55,393 $2,760
55,393
kWh
05: 2.8123 PAY UTILITY BILLS ON TIME Savings:
$540
Cost:
-
$540 - $540
-
kWh
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$150
Cost:
-
$150 2,931 $150
2,931
kWh
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$120
Cost:
-
$120 2,345 $120
2,345
kWh
TOTAL RECOMMENDED Savings:
$28,150
Cost:
$27,770
$28,150 361,080 $28,150
361,080
kWh
TOTAL IMPLEMENTED Savings:
$19,140
Cost:
$1,570
$19,140 352,287 $19,140
352,287
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage