IAC Assessment: AM0208
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0208
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 1994
Principal Product Windshield solvent, hair spray, tire repair sealants, auto c
NAICS n/a
SIC 2842 - Polishes And Sanitation Goods
Sales $10,000,000-$50,000,000
# of Employees 140
Plant Area (Sq.Ft.) 95,000
Annual Production 33,410,000 Pieces
Production Hrs. Annual 2,024
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $127,225 1,572,978 kWh $0.08
Natural Gas $11,977 2,603 MMBtu $4.60
TOTAL ENERGY COSTS $139,202
RECOMMENDED SAVINGS* $27,575 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $27,575
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$13,375
Cost:
$16,000
- - - - $13,375 - -
-
kWh
-
-
MMBtu
$13,375
-
$
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$6,550
Cost:
$2,135
$6,550 111,665 - - - - $6,550
111,665
kWh
-
-
MMBtu
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,265
Cost:
$5,320
$4,265 84,115 - - - - $4,265
84,115
kWh
-
-
MMBtu
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,570
Cost:
$5,850
$2,570 27,550 - - - - $2,570
27,550
kWh
-
-
MMBtu
-
-
$
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$815
Cost:
$1,535
- - $815 167 - - -
-
kWh
$815
167
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$27,575
Cost:
$30,840
$13,385 223,330 $815 167 $13,375 - $13,385
223,330
kWh
$815
167
MMBtu
$13,375
-
$
TOTAL IMPLEMENTED Savings:
$27,575
Cost:
$30,840
$13,385 223,330 $815 167 $13,375 - $13,385
223,330
kWh
$815
167
MMBtu
$13,375
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes