IAC Assessment: AM0283
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0283
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 1996
Principal Product Frozen desserts
NAICS n/a
SIC 2024 - Ice Cream And Frozen Desserts
Sales $50,000,000-$100,000,000
# of Employees 140
Plant Area (Sq.Ft.) 158,000
Annual Production 12,500 Thousand Gallons
Production Hrs. Annual 7,488
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $582,310 16,487,984 kWh $0.04
Electricity Demand $237,130 36,363 kW-months/year $6.52
Natural Gas $45,273 9,194 MMBtu $4.92
TOTAL ENERGY COSTS $864,713
RECOMMENDED SAVINGS* $58,440 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $57,300
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ $
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$43,960
Cost:
$40,000
- - $43,960 3,571 - - - - - - - - -
-
kWh
$43,960
3,571
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$1,860
Cost:
$500
- - - - $1,860 377 - - - - - - -
-
kWh
-
-
kW-months/year
$1,860
377
MMBtu
-
-
Tgal
-
-
lb
-
-
$
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1,940
Cost:
$4,320
$370 16,706 $310 25 $1,260 255 - - - - - - $370
16,706
kWh
$310
25
kW-months/year
$1,260
255
MMBtu
-
-
Tgal
-
-
lb
-
-
$
04: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$1,570
Cost:
$100
- - - - $1,570 320 - - - - - - -
-
kWh
-
-
kW-months/year
$1,570
320
MMBtu
-
-
Tgal
-
-
lb
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,140
Cost:
$1,180
$200 9,086 $150 12 - - - - - - $790 - $200
9,086
kWh
$150
12
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
$790
-
$
06: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES Savings:
$5,900
Cost:
$100
- - - - - - $5,900 2,927,300 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$5,900
2,927,300
Tgal
-
-
lb
-
-
$
07: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$2,070
Cost:
-
- - - - - - - - $2,070 41,300 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$2,070
41,300
lb
-
-
$
TOTAL RECOMMENDED Savings:
$58,440
Cost:
$46,200
$570 25,792 $44,420 3,608 $4,690 952 $5,900 2,927,300 $2,070 41,300 $790 - $570
25,792
kWh
$44,420
3,608
kW-months/year
$4,690
952
MMBtu
$5,900
2,927,300
Tgal
$2,070
41,300
lb
$790
-
$
TOTAL IMPLEMENTED Savings:
$57,300
Cost:
$45,020
$370 16,706 $44,270 3,596 $4,690 952 $5,900 2,927,300 $2,070 41,300 - - $370
16,706
kWh
$44,270
3,596
kW-months/year
$4,690
952
MMBtu
$5,900
2,927,300
Tgal
$2,070
41,300
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes