Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1997 |
Principal Product | Barges, repaired & built |
NAICS | n/a |
SIC | 3731 - Ship Building And Repairing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 260 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,750 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $267,948 | 7,868,699 | kWh | $0.03 |
Electricity Demand | $107,635 | 17,316 | kW-months/year | $6.22 |
Electricity Fees | $27,541 | - | $ | - |
Natural Gas | $161,402 | 46,342 | MMBtu | $3.48 |
TOTAL ENERGY COSTS | $564,526 | |||
RECOMMENDED SAVINGS* | $16,750 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,000 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $4,660 Cost: $920 |
- | - | - | - | $4,660 | 1,340 |
- - kWh |
- - kW-months/year |
$4,660 1,340 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $3,310 Cost: $500 |
- | - | - | - | $3,310 | 950 |
- - kWh |
- - kW-months/year |
$3,310 950 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION |
Savings: $3,100 Cost: - |
- | - | $3,100 | 252 | - | - |
- - kWh |
$3,100 252 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $2,130 Cost: - |
$1,120 | 50,996 | $1,010 | 82 | - | - |
$1,120 50,996 kWh |
$1,010 82 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,500 Cost: $300 |
- | - | - | - | $1,500 | 431 |
- - kWh |
- - kW-months/year |
$1,500 431 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $1,300 Cost: $150 |
$440 | 19,930 | $860 | 70 | - | - |
$440 19,930 kWh |
$860 70 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $750 Cost: - |
$750 | 34,291 | - | - | - | - |
$750 34,291 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $16,750 Cost: $1,870 |
$2,310 | 105,217 | $4,970 | 404 | $9,470 | 2,721 | $2,310 105,217 kWh |
$4,970 404 kW-months/year |
$9,470 2,721 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,000 Cost: $1,870 |
$1,560 | 70,926 | $4,970 | 404 | $9,470 | 2,721 | $1,560 70,926 kWh |
$4,970 404 kW-months/year |
$9,470 2,721 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |