Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1998 |
Principal Product | Milk, ice cream |
NAICS | n/a |
SIC | 2026 - Fluid Milk |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 42,000 |
Annual Production | 21,600 Thousand Gallons |
Production Hrs. Annual | 5,900 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $153,687 | 8,499,414 | kWh | $0.02 |
Electricity Demand | $265,913 | 19,768 | kW-months/year | $13.45 |
Electricity Fees | $3,865 | - | $ | - |
Natural Gas | $110,140 | 26,300 | MMBtu | $4.19 |
TOTAL ENERGY COSTS | $801,748 | |||
RECOMMENDED SAVINGS* | $193,536 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $49,011 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.6113 REMOVE SLUDGE FROM TANKS ON A REGULAR BASIS |
Savings: $116,000 Cost: $900,000 |
- | - | - | - | - | - | $116,000 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$116,000 - Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8118 CHECK FOR ACCURACY OF UTILITY / POWER METERS |
Savings: $31,316 Cost: - |
- | - | $31,316 | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$31,316 - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.1291 ELIMINATE PRACTICE OF MIXING WASTE STREAMS |
Savings: $23,800 Cost: $1,515 |
- | - | - | - | - | - | - | - | $23,800 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$23,800 - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $11,300 Cost: $340 |
$11,300 | 348,769 | - | - | - | - | - | - | - | - | - | - | - | - |
$11,300 348,769 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $2,785 Cost: - |
$1,665 | 51,583 | $1,120 | 84 | - | - | - | - | - | - | - | - | - | - |
$1,665 51,583 kWh |
$1,120 84 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $2,170 Cost: - |
- | - | - | - | - | - | - | - | - | - | $2,170 | 14,450 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
$2,170 14,450 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES |
Savings: $1,620 Cost: $1,010 |
- | - | - | - | $460 | 111 | $1,160 | 690,000 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$460 111 MMBtu |
$1,160 690,000 Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,500 Cost: $2,100 |
$920 | 28,429 | $580 | 44 | - | - | - | - | - | - | - | - | - | - |
$920 28,429 kWh |
$580 44 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $1,400 Cost: - |
$985 | 30,481 | $415 | 31 | - | - | - | - | - | - | - | - | - | - |
$985 30,481 kWh |
$415 31 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $1,105 Cost: $1,205 |
$220 | 6,741 | $120 | 9 | - | - | - | - | - | - | - | - | $765 | - |
$220 6,741 kWh |
$120 9 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
$765 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $290 Cost: $93 |
$160 | 4,982 | $130 | 10 | - | - | - | - | - | - | - | - | - | - |
$160 4,982 kWh |
$130 10 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $250 Cost: $485 |
$250 | 7,913 | - | - | - | - | - | - | - | - | - | - | - | - |
$250 7,913 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $193,536 Cost: $906,748 |
$15,500 | 478,898 | $33,681 | 178 | $460 | 111 | $117,160 | 690,000 | $23,800 | - | $2,170 | 14,450 | $765 | - | $15,500 478,898 kWh |
$33,681 178 kW-months/year |
$460 111 MMBtu |
$117,160 690,000 Tgal |
$23,800 - gal |
$2,170 14,450 lb |
$765 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $49,011 Cost: $4,655 |
$12,440 | 383,939 | $32,016 | 53 | $460 | 111 | $1,160 | 690,000 | - | - | $2,170 | 14,450 | $765 | - | $12,440 383,939 kWh |
$32,016 53 kW-months/year |
$460 111 MMBtu |
$1,160 690,000 Tgal |
- - gal |
$2,170 14,450 lb |
$765 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes |