Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2000 |
Principal Product | Refrigeration and other control valves |
NAICS | n/a |
SIC | 3491 - Industrial Valves |
Sales | $10,000,000-$50,000,000 |
# of Employees | 215 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 1,750,000 Pounds |
Production Hrs. Annual | 5,072 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $91,765 | 1,987,397 | kWh | $0.05 |
Electricity Demand | $17,641 | 5,428 | kW-months/year | $3.25 |
Natural Gas | $6,019 | 1,439 | MMBtu | $4.18 |
TOTAL ENERGY COSTS | $128,275 | |||
RECOMMENDED SAVINGS* | $20,535 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,255 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.7191 USE WATER BASED SPRAY ABRASIVES INSTEAD OF BAR ABRASIVES |
Savings: $13,500 Cost: $70,000 |
- | - | - | - | $13,500 | 10,100 | - | - |
- - kWh |
- - kW-months/year |
$13,500 10,100 gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,540 Cost: $500 |
$4,540 | 105,510 | - | - | - | - | - | - |
$4,540 105,510 kWh |
- - kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,245 Cost: $210 |
$1,000 | 23,154 | $245 | 55 | - | - | - | - |
$1,000 23,154 kWh |
$245 55 kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $600 Cost: $180 |
$600 | 13,775 | - | - | - | - | - | - |
$600 13,775 kWh |
- - kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $470 Cost: $215 |
$60 | 1,465 | $10 | 2 | - | - | $400 | - |
$60 1,465 kWh |
$10 2 kW-months/year |
- - gal |
$400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $180 Cost: - |
$145 | 3,224 | $35 | 8 | - | - | - | - |
$145 3,224 kWh |
$35 8 kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $20,535 Cost: $71,105 |
$6,345 | 147,128 | $290 | 65 | $13,500 | 10,100 | $400 | - | $6,345 147,128 kWh |
$290 65 kW-months/year |
$13,500 10,100 gal |
$400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,255 Cost: $925 |
$5,600 | 130,129 | $255 | 57 | - | - | $400 | - | $5,600 130,129 kWh |
$255 57 kW-months/year |
- - gal |
$400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes |