Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2002 |
Principal Product | Abrasive blasting and recovery equipment |
NAICS | n/a |
SIC | 3559 - Special Industry Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 56 |
Plant Area (Sq.Ft.) | 85,000 |
Annual Production | 4,200 Pieces |
Production Hrs. Annual | 2,068 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $73,809 | 1,025,856 | kWh | $0.07 |
Electricity Demand | $19,725 | 6,483 | kW-months/year | $3.04 |
TOTAL ENERGY COSTS | $93,534 | |||
RECOMMENDED SAVINGS* | $25,853 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $23,493 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $10,660 Cost: $15,375 |
- | - | $10,660 | 1,945 | - | - | - | - | - | - |
- - kWh |
$10,660 1,945 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $5,870 Cost: $12,210 |
$5,870 | 83,700 | - | - | - | - | - | - | - | - |
$5,870 83,700 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,120 Cost: $6,440 |
$1,630 | 23,320 | $490 | 90 | - | - | - | - | - | - |
$1,630 23,320 kWh |
$490 90 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.7132 REUSE RAGS UNTIL COMPLETELY SOILED |
Savings: $1,850 Cost: - |
- | - | - | - | $1,850 | 1,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,850 1,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,600 Cost: $800 |
$1,600 | 22,800 | - | - | - | - | - | - | - | - |
$1,600 22,800 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $1,140 Cost: - |
$1,140 | 16,300 | - | - | - | - | - | - | - | - |
$1,140 16,300 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $840 Cost: $170 |
$840 | 12,000 | - | - | - | - | - | - | - | - |
$840 12,000 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $800 Cost: $300 |
$140 | 2,000 | $15 | 3 | - | - | $645 | - | - | - |
$140 2,000 kWh |
$15 3 kW-months/year |
- - lb |
$645 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE |
Savings: $720 Cost: - |
- | - | - | - | - | - | - | - | $720 | - |
- - kWh |
- - kW-months/year |
- - lb |
- - $ |
$720 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $253 Cost: - |
- | - | - | - | - | - | $253 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$253 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,853 Cost: $35,295 |
$11,220 | 160,120 | $11,165 | 2,038 | $1,850 | 1,000 | $898 | - | $720 | - | $11,220 160,120 kWh |
$11,165 2,038 kW-months/year |
$1,850 1,000 lb |
$898 - $ |
$720 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $23,493 Cost: $34,825 |
$10,240 | 146,120 | $11,150 | 2,035 | $1,850 | 1,000 | $253 | - | - | - | $10,240 146,120 kWh |
$11,150 2,035 kW-months/year |
$1,850 1,000 lb |
$253 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |