Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2002 |
Principal Product | Machinery noise control equipment |
NAICS | n/a |
SIC | 3569 - General Industrial Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 23,000 |
Annual Production | 12,000 Tons |
Production Hrs. Annual | 1,990 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $46,548 | 560,256 | kWh | $0.08 |
Electricity Demand | $6,975 | 2,370 | kW-months/year | $2.94 |
Electricity Fees | $592 | - | $ | - |
TOTAL ENERGY COSTS | $54,115 | |||
RECOMMENDED SAVINGS* | $64,760 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,035 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.446 AUTOMATE FINISHING PROCESS |
Savings: $47,350 Cost: $110,240 |
- | - | $1,250 | 205 | $46,100 | - | - | - | - | - |
- - kWh |
$1,250 205 kW-months/year |
$46,100 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE |
Savings: $13,580 Cost: $5,270 |
- | - | - | - | $1,520 | - | - | - | $12,060 | - |
- - kWh |
- - kW-months/year |
$1,520 - $ |
- - $ |
$12,060 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,545 Cost: $30 |
$970 | 14,200 | $575 | 94 | - | - | - | - | - | - |
$970 14,200 kWh |
$575 94 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $780 Cost: $50 |
$590 | 8,600 | $190 | 31 | - | - | - | - | - | - |
$590 8,600 kWh |
$190 31 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $645 Cost: - |
- | - | - | - | - | - | $645 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$645 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $375 Cost: $840 |
- | - | $375 | 61 | - | - | - | - | - | - |
- - kWh |
$375 61 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $345 Cost: $310 |
$160 | 2,330 | $20 | 3 | $165 | - | - | - | - | - |
$160 2,330 kWh |
$20 3 kW-months/year |
$165 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $140 Cost: $50 |
$140 | 2,080 | - | - | - | - | - | - | - | - |
$140 2,080 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $64,760 Cost: $116,790 |
$1,860 | 27,210 | $2,410 | 394 | $47,785 | - | $645 | - | $12,060 | - | $1,860 27,210 kWh |
$2,410 394 kW-months/year |
$47,785 - $ |
$645 - $ |
$12,060 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,035 Cost: $5,710 |
$1,860 | 27,210 | $785 | 128 | $1,685 | - | $645 | - | $12,060 | - | $1,860 27,210 kWh |
$785 128 kW-months/year |
$1,685 - $ |
$645 - $ |
$12,060 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost |