IAC Assessment: AM0426
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0426
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2003
Principal Product Composite Aircraft Engine Fan Blades
NAICS 336412 - Aircraft Engine and Engine Parts Manufacturing
SIC 3724 - Aircraft Engines And Engine Parts
Sales $50,000,000-$100,000,000
# of Employees 150
Plant Area (Sq.Ft.) 160,000
Annual Production 1,000 Pieces
Production Hrs. Annual 6,024
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $447,246 9,172,000 kWh $0.05
Electricity Demand $34,628 20,860 kW-months/year $1.66
Natural Gas $56,358 8,330 MMBtu $6.77
TOTAL ENERGY COSTS $538,232
RECOMMENDED SAVINGS* $12,830 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $820
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes
$ kWh $ kW-months/year $ lb $ $
01: 3.7132 REUSE RAGS UNTIL COMPLETELY SOILED Savings:
$5,330
Cost:
-
- - - - $5,330 - - - -
-
kWh
-
-
kW-months/year
$5,330
-
lb
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,310
Cost:
$1,460
$610 12,980 $30 18 - - $2,670 - $610
12,980
kWh
$30
18
kW-months/year
-
-
lb
$2,670
-
$
03: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$1,950
Cost:
-
$1,950 41,590 - - - - - - $1,950
41,590
kWh
-
-
kW-months/year
-
-
lb
-
-
$
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$1,420
Cost:
-
$1,420 30,240 - - - - - - $1,420
30,240
kWh
-
-
kW-months/year
-
-
lb
-
-
$
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$820
Cost:
$500
$820 17,400 - - - - - - $820
17,400
kWh
-
-
kW-months/year
-
-
lb
-
-
$
TOTAL RECOMMENDED Savings:
$12,830
Cost:
$1,960
$4,800 102,210 $30 18 $5,330 - $2,670 - $4,800
102,210
kWh
$30
18
kW-months/year
$5,330
-
lb
$2,670
-
$
TOTAL IMPLEMENTED Savings:
$820
Cost:
$500
$820 17,400 - - - - - - $820
17,400
kWh
-
-
kW-months/year
-
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes