Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2003 |
Principal Product | Electroplating |
NAICS | 332813 - Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471 - Plating And Polishing |
Sales | $5,000,000-$10,000,000 |
# of Employees | 68 |
Plant Area (Sq.Ft.) | 17,900 |
Annual Production | 365,000 Pieces |
Production Hrs. Annual | 4,630 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $64,536 | 918,774 | kWh | $0.07 |
Electricity Demand | $8,822 | 3,507 | kW-months/year | $2.52 |
Electricity Fees | $1,334 | - | $ | - |
Natural Gas | $543 | 8 | MMBtu | $67.88 |
TOTAL ENERGY COSTS | $75,235 | |||
RECOMMENDED SAVINGS* | $15,220 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,220 |
#|Description |
Savings Cost |
Status | Electricity Usage | Personnel Changes | Primary Raw Material | Electricity Usage | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.132 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST |
Savings: $11,250 Cost: $500 |
- | - | - | - | $11,250 | - |
- - kWh |
- - $ |
$11,250 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,400 Cost: $820 |
$260 | 5,400 | $2,140 | - | - | - |
$260 5,400 kWh |
$2,140 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $570 Cost: $60 |
$570 | 11,625 | - | - | - | - |
$570 11,625 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $400 Cost: - |
$400 | 8,150 | - | - | - | - |
$400 8,150 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $330 Cost: $60 |
$330 | 6,730 | - | - | - | - |
$330 6,730 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $170 Cost: $50 |
$170 | 3,500 | - | - | - | - |
$170 3,500 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $100 Cost: $50 |
$100 | 2,300 | - | - | - | - |
$100 2,300 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $15,220 Cost: $1,540 |
$1,830 | 37,705 | $2,140 | - | $11,250 | - | $1,830 37,705 kWh |
$2,140 - $ |
$11,250 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,220 Cost: $1,540 |
$1,830 | 37,705 | $2,140 | - | $11,250 | - | $1,830 37,705 kWh |
$2,140 - $ |
$11,250 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Personnel Changes | Primary Raw Material | Electricity Usage | Personnel Changes | Primary Raw Material |