Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2006 |
Principal Product | Beef cows slaughtered |
NAICS | 311612 - Meat Processed from Carcasses |
SIC | 2011 - Meat Packing Plants |
Sales | $100,000,000-$500,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 55,000 |
Annual Production | 170,000 Pieces |
Production Hrs. Annual | 7,344 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $516,233 | 12,785,600 | kWh | $0.04 |
Electricity Demand | $209,682 | 28,992 | kW-months/year | $7.23 |
Electricity Fees | $42,354 | - | $ | - |
Natural Gas | $939,206 | 108,221 | MMBtu | $8.68 |
TOTAL ENERGY COSTS | $1,707,475 | |||
RECOMMENDED SAVINGS* | $172,627 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $143,011 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8112 COMBINE UTILITY METERS |
Savings: $71,000 Cost: $100,000 |
- | - | - | - | $71,000 | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$71,000 - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.132 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST |
Savings: $37,900 Cost: $600 |
- | - | - | - | - | - | - | - | - | - | $37,900 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
$37,900 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $22,000 Cost: $51,000 |
- | - | - | - | - | - | $22,000 | 2,163 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$22,000 2,163 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $13,750 Cost: $2,100 |
- | - | - | - | - | - | $13,750 | 1,355 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$13,750 1,355 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.8221 USE ALTERNATIVES FOR ACIDS / ALKALINE (WATER, STEAM, ABRASIVE) |
Savings: $7,616 Cost: $25,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $7,616 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
$7,616 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $9,000 Cost: $500 |
- | - | - | - | - | - | $9,000 | 887 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$9,000 887 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,240 Cost: $400 |
$2,500 | 55,100 | $740 | 90 | - | - | - | - | - | - | - | - | - | - |
$2,500 55,100 kWh |
$740 90 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,900 Cost: $9,900 |
$2,200 | 48,400 | $700 | 85 | - | - | - | - | - | - | - | - | - | - |
$2,200 48,400 kWh |
$700 85 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,430 Cost: $1,620 |
$1,900 | 42,040 | $530 | 65 | - | - | - | - | - | - | - | - | - | - |
$1,900 42,040 kWh |
$530 65 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $733 Cost: - |
$565 | 12,450 | $168 | 20 | - | - | - | - | - | - | - | - | - | - |
$565 12,450 kWh |
$168 20 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,120 Cost: $100 |
$700 | 15,350 | $420 | 50 | - | - | - | - | - | - | - | - | - | - |
$700 15,350 kWh |
$420 50 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $938 Cost: $215 |
$360 | 8,065 | $160 | 19 | - | - | - | - | $418 | - | - | - | - | - |
$360 8,065 kWh |
$160 19 kW-months/year |
- - $ |
- - MMBtu |
$418 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $172,627 Cost: $191,435 |
$8,225 | 181,405 | $2,718 | 329 | $71,000 | - | $44,750 | 4,405 | $418 | - | $37,900 | - | $7,616 | - | $8,225 181,405 kWh |
$2,718 329 kW-months/year |
$71,000 - $ |
$44,750 4,405 MMBtu |
$418 - $ |
$37,900 - $ |
$7,616 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $143,011 Cost: $115,435 |
$8,225 | 181,405 | $2,718 | 329 | $71,000 | - | $22,750 | 2,242 | $418 | - | $37,900 | - | - | - | $8,225 181,405 kWh |
$2,718 329 kW-months/year |
$71,000 - $ |
$22,750 2,242 MMBtu |
$418 - $ |
$37,900 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Primary Raw Material | Ancillary Material Cost |