Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2007 |
Principal Product | White & yellow mineral oil |
NAICS | 324199 - All Other Petroleum and Coal Products Manufacturing |
SIC | 2999 - Petroleum And Coal Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 80 |
Plant Area (Sq.Ft.) | 30,000 |
Annual Production | 8,603 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $317,663 | 4,798,901 | kWh | $0.07 |
Electricity Demand | $72,414 | 10,661 | kW-months/year | $6.79 |
Electricity Fees | $1,182 | - | $ | - |
Natural Gas | $692,460 | 88,152 | MMBtu | $7.86 |
TOTAL ENERGY COSTS | $1,083,719 | |||
RECOMMENDED SAVINGS* | $102,850 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $94,850 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $65,000 Cost: $1,100 |
- | - | - | - | $65,000 | 8,240 | - | - |
- - kWh |
- - kW-months/year |
$65,000 8,240 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $24,700 Cost: $500 |
- | - | - | - | $24,700 | 3,150 | - | - |
- - kWh |
- - kW-months/year |
$24,700 3,150 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $8,000 Cost: $31,200 |
- | - | - | - | $8,000 | 1,020 | - | - |
- - kWh |
- - kW-months/year |
$8,000 1,020 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,000 Cost: $380 |
$180 | 2,450 | $20 | 3 | - | - | $800 | - |
$180 2,450 kWh |
$20 3 kW-months/year |
- - MMBtu |
$800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $1,740 Cost: - |
$1,740 | 24,100 | - | - | - | - | - | - |
$1,740 24,100 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,300 Cost: $280 |
- | - | - | - | $1,300 | 153 | - | - |
- - kWh |
- - kW-months/year |
$1,300 153 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $810 Cost: - |
$685 | 9,500 | $125 | 17 | - | - | - | - |
$685 9,500 kWh |
$125 17 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $300 Cost: - |
$300 | 4,100 | - | - | - | - | - | - |
$300 4,100 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $102,850 Cost: $33,460 |
$2,905 | 40,150 | $145 | 20 | $99,000 | 12,563 | $800 | - | $2,905 40,150 kWh |
$145 20 kW-months/year |
$99,000 12,563 MMBtu |
$800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $94,850 Cost: $2,260 |
$2,905 | 40,150 | $145 | 20 | $91,000 | 11,543 | $800 | - | $2,905 40,150 kWh |
$145 20 kW-months/year |
$91,000 11,543 MMBtu |
$800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |