IAC Assessment: AM0530
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0530
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2007
Principal Product Oil Field Equipment
NAICS 333132 - Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3533 - Oil And Gas Field Machinery
Sales $10,000,000-$50,000,000
# of Employees 53
Plant Area (Sq.Ft.) 61,800
Annual Production 853 Tons
Production Hrs. Annual 7,270
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $77,477 1,199,652 kWh $0.06
Electricity Demand $27,521 5,292 kW-months/year $5.20
TOTAL ENERGY COSTS $104,998
RECOMMENDED SAVINGS* $23,955 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $10,930
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Personnel Changes Primary Raw Material
$ kWh $ kW-months/year $ $ $ $
01: 4.214 PURCHASE APPROPRIATELY SIZED MATERIAL Savings:
$13,025
Cost:
$500
- - - - $225 - $12,800 - -
-
kWh
-
-
kW-months/year
$225
-
$
$12,800
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$8,000
Cost:
$38,913
$7,000 97,800 $1,000 190 - - - - $7,000
97,800
kWh
$1,000
190
kW-months/year
-
-
$
-
-
$
03: 2.7123 KEEP LAMPS AND REFLECTORS CLEAN Savings:
$880
Cost:
-
$990 13,780 - - $(-110) - - - $990
13,780
kWh
-
-
kW-months/year
$(-110)
-
$
-
-
$
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$670
Cost:
-
$670 9,800 - - - - - - $670
9,800
kWh
-
-
kW-months/year
-
-
$
-
-
$
05: 2.7134 USE PHOTOCELL CONTROLS Savings:
$620
Cost:
$45
$500 7,000 $120 25 - - - - $500
7,000
kWh
$120
25
kW-months/year
-
-
$
-
-
$
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$430
Cost:
-
$430 6,000 - - - - - - $430
6,000
kWh
-
-
kW-months/year
-
-
$
-
-
$
07: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$330
Cost:
-
$290 3,980 $40 8 - - - - $290
3,980
kWh
$40
8
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$23,955
Cost:
$39,458
$9,880 138,360 $1,160 223 $115 - $12,800 - $9,880
138,360
kWh
$1,160
223
kW-months/year
$115
-
$
$12,800
-
$
TOTAL IMPLEMENTED Savings:
$10,930
Cost:
$38,958
$9,880 138,360 $1,160 223 $(-110) - - - $9,880
138,360
kWh
$1,160
223
kW-months/year
$(-110)
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Personnel Changes Primary Raw Material