Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2007 |
Principal Product | Oil Field Equipment |
NAICS | 333132 - Oil and Gas Field Machinery and Equipment Manufacturing |
SIC | 3533 - Oil And Gas Field Machinery |
Sales | $10,000,000-$50,000,000 |
# of Employees | 53 |
Plant Area (Sq.Ft.) | 61,800 |
Annual Production | 853 Tons |
Production Hrs. Annual | 7,270 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $77,477 | 1,199,652 | kWh | $0.06 |
Electricity Demand | $27,521 | 5,292 | kW-months/year | $5.20 |
TOTAL ENERGY COSTS | $104,998 | |||
RECOMMENDED SAVINGS* | $23,955 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,930 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.214 PURCHASE APPROPRIATELY SIZED MATERIAL |
Savings: $13,025 Cost: $500 |
- | - | - | - | $225 | - | $12,800 | - |
- - kWh |
- - kW-months/year |
$225 - $ |
$12,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $8,000 Cost: $38,913 |
$7,000 | 97,800 | $1,000 | 190 | - | - | - | - |
$7,000 97,800 kWh |
$1,000 190 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7123 KEEP LAMPS AND REFLECTORS CLEAN |
Savings: $880 Cost: - |
$990 | 13,780 | - | - | $(-110) | - | - | - |
$990 13,780 kWh |
- - kW-months/year |
$(-110) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $670 Cost: - |
$670 | 9,800 | - | - | - | - | - | - |
$670 9,800 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $620 Cost: $45 |
$500 | 7,000 | $120 | 25 | - | - | - | - |
$500 7,000 kWh |
$120 25 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $430 Cost: - |
$430 | 6,000 | - | - | - | - | - | - |
$430 6,000 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $330 Cost: - |
$290 | 3,980 | $40 | 8 | - | - | - | - |
$290 3,980 kWh |
$40 8 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $23,955 Cost: $39,458 |
$9,880 | 138,360 | $1,160 | 223 | $115 | - | $12,800 | - | $9,880 138,360 kWh |
$1,160 223 kW-months/year |
$115 - $ |
$12,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,930 Cost: $38,958 |
$9,880 | 138,360 | $1,160 | 223 | $(-110) | - | - | - | $9,880 138,360 kWh |
$1,160 223 kW-months/year |
$(-110) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Personnel Changes | Primary Raw Material |