IAC Assessment: AM0572
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0572
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2010
Principal Product Truck trailers
NAICS 336212 - Truck Trailer Manufacturing
SIC 3715 - Truck Trailers
Sales $50,000,000-$100,000,000
# of Employees 200
Plant Area (Sq.Ft.) 272,000
Annual Production 324 Pieces
Production Hrs. Annual 2,000
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $221,211 2,538,178 kWh $0.09
Electricity Demand $90,917 12,026 kW-months/year $7.56
Natural Gas $58,799 6,063 MMBtu $9.70
TOTAL ENERGY COSTS $370,927
RECOMMENDED SAVINGS* $22,765 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $22,425
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$10,200
Cost:
$34,000
$6,800 75,500 $3,400 453 - - - - $6,800
75,500
kWh
$3,400
453
kW-months/year
-
-
$
-
-
$
02: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$6,050
Cost:
-
$4,100 45,565 $1,950 258 - - - - $4,100
45,565
kWh
$1,950
258
kW-months/year
-
-
$
-
-
$
03: 2.8123 PAY UTILITY BILLS ON TIME Savings:
$1,925
Cost:
-
- - - - $1,925 - - - -
-
kWh
-
-
kW-months/year
$1,925
-
$
-
-
$
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,200
Cost:
$3,250
- - $1,200 159 - - - - -
-
kWh
$1,200
159
kW-months/year
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,025
Cost:
$460
$260 2,900 $30 4 - - $735 - $260
2,900
kWh
$30
4
kW-months/year
-
-
$
$735
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$800
Cost:
$400
$530 5,900 $270 36 - - - - $530
5,900
kWh
$270
36
kW-months/year
-
-
$
-
-
$
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$725
Cost:
$350
$485 5,400 $240 32 - - - - $485
5,400
kWh
$240
32
kW-months/year
-
-
$
-
-
$
08: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$500
Cost:
-
$500 5,560 - - - - - - $500
5,560
kWh
-
-
kW-months/year
-
-
$
-
-
$
09: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$340
Cost:
-
- - - - - - $340 - -
-
kWh
-
-
kW-months/year
-
-
$
$340
-
$
TOTAL RECOMMENDED Savings:
$22,765
Cost:
$38,460
$12,675 140,825 $7,090 942 $1,925 - $1,075 - $12,675
140,825
kWh
$7,090
942
kW-months/year
$1,925
-
$
$1,075
-
$
TOTAL IMPLEMENTED Savings:
$22,425
Cost:
$38,460
$12,675 140,825 $7,090 942 $1,925 - $735 - $12,675
140,825
kWh
$7,090
942
kW-months/year
$1,925
-
$
$735
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost