Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2012 |
Principal Product | Valve assemblies |
NAICS | 332919 - Other Metal Valve and Pipe Fitting Manufacturing |
SIC | 3494 - Valves And Pipe Fittings, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 60,000 Pieces |
Production Hrs. Annual | 6,279 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $146,607 | 2,253,015 | kWh | $0.07 |
Electricity Demand | $48,472 | 6,974 | kW-months/year | $6.95 |
Electricity Fees | $1,617 | - | $ | - |
TOTAL ENERGY COSTS | $196,696 | |||
RECOMMENDED SAVINGS* | $31,295 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $24,210 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $17,100 Cost: $33,600 |
$14,200 | 253,200 | $2,900 | 520 | - | - | - | - |
$14,200 253,200 kWh |
$2,900 520 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $5,450 Cost: $18,900 |
- | - | $5,450 | 969 | - | - | - | - |
- - kWh |
$5,450 969 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,375 Cost: $2,490 |
$5,375 | 96,000 | - | - | - | - | - | - |
$5,375 96,000 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $960 Cost: $440 |
$150 | 2,660 | $20 | 4 | $790 | - | - | - |
$150 2,660 kWh |
$20 4 kW-months/year |
$790 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $850 Cost: $381 |
$850 | 15,155 | - | - | - | - | - | - |
$850 15,155 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $605 Cost: - |
$460 | 8,270 | $145 | 26 | - | - | - | - |
$460 8,270 kWh |
$145 26 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $280 Cost: $381 |
$280 | 5,000 | - | - | - | - | - | - |
$280 5,000 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $675 Cost: - |
- | - | - | - | - | - | $675 | - |
- - kWh |
- - kW-months/year |
- - $ |
$675 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $31,295 Cost: $56,192 |
$21,315 | 380,285 | $8,515 | 1,519 | $790 | - | $675 | - | $21,315 380,285 kWh |
$8,515 1,519 kW-months/year |
$790 - $ |
$675 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $24,210 Cost: $36,852 |
$21,165 | 377,625 | $3,045 | 546 | - | - | - | - | $21,165 377,625 kWh |
$3,045 546 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost |