IAC logo
IAC Assessment: AM0681
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0681
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2015
Principal Product Life jackets and vests
NAICS 339920 - Sporting and Athletic Goods Manufacturing
SIC 3069 - Fabricated Rubber Products, Nec
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 170,000
Annual Production 1,000,000 Pieces
Production Hrs. Annual 2,236
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $36,088 603,200 kWh $0.06
Electricity Demand $22,153 2,202 kW-months/year $10.06
Electricity Fees $6,027 - $ -
TOTAL ENERGY COSTS $64,268
RECOMMENDED SAVINGS* $23,422 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $22,569
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Personnel Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,953
Cost:
$11,375
$2,609 43,485 $2,344 233 - - - - - - $2,609
43,485
kWh
$2,344
233
kW-months/year
-
-
$
-
-
$
-
-
$
02: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$14,391
Cost:
$5,000
- - - - $4,797 - - - $9,594 - -
-
kWh
-
-
kW-months/year
$4,797
-
$
-
-
$
$9,594
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$2,120
Cost:
$1,125
$2,120 35,286 - - - - - - - - $2,120
35,286
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$853
Cost:
$430
$150 2,505 $30 3 - - $673 - - - $150
2,505
kWh
$30
3
kW-months/year
-
-
$
$673
-
$
-
-
$
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$741
Cost:
$1,240
$389 6,479 $352 35 - - - - - - $389
6,479
kWh
$352
35
kW-months/year
-
-
$
-
-
$
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$364
Cost:
$182
$193 3,213 $171 17 - - - - - - $193
3,213
kWh
$171
17
kW-months/year
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$23,422
Cost:
$19,352
$5,461 90,968 $2,897 288 $4,797 - $673 - $9,594 - $5,461
90,968
kWh
$2,897
288
kW-months/year
$4,797
-
$
$673
-
$
$9,594
-
$
TOTAL IMPLEMENTED Savings:
$22,569
Cost:
$18,922
$5,311 88,463 $2,867 285 $4,797 - - - $9,594 - $5,311
88,463
kWh
$2,867
285
kW-months/year
$4,797
-
$
-
-
$
$9,594
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Personnel Changes One-time Revenue or Avoided Cost