Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2018 |
Principal Product | Wheelchair accessories |
NAICS | 339999 - All Other Miscellaneous Manufacturing |
SIC | 3599 - Industrial Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 1,500,000 Pieces |
Production Hrs. Annual | 6,024 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $95,535 | 939,696 | kWh | $0.10 |
Electricity Demand | $6,494 | 3,243 | kW-months/year | $2.00 |
TOTAL ENERGY COSTS | $107,849 | |||
RECOMMENDED SAVINGS* | $5,660 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,360 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $450 Cost: $1,970 |
$880 | 8,500 | $60 | 29 | $590 | - | $(-1,080) | - |
$880 8,500 kWh |
$60 29 kW-months/year |
$590 - $ |
$(-1,080) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,310 Cost: $3,750 |
$1,180 | 11,300 | $130 | 66 | - | - | - | - |
$1,180 11,300 kWh |
$130 66 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,175 Cost: $500 |
$1,130 | 10,840 | $45 | 22 | - | - | - | - |
$1,130 10,840 kWh |
$45 22 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,040 Cost: $1,070 |
$1,040 | 10,000 | - | - | - | - | - | - |
$1,040 10,000 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $555 Cost: $540 |
$555 | 5,350 | - | - | - | - | - | - |
$555 5,350 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $425 Cost: $205 |
$122 | 1,180 | $3 | 2 | $300 | - | - | - |
$122 1,180 kWh |
$3 2 kW-months/year |
$300 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $450 Cost: $30 |
$430 | 4,130 | $20 | 11 | - | - | - | - |
$430 4,130 kWh |
$20 11 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $255 Cost: $4 |
$235 | 2,250 | $20 | 9 | - | - | - | - |
$235 2,250 kWh |
$20 9 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $5,660 Cost: $8,069 |
$5,572 | 53,550 | $278 | 139 | $890 | - | $(-1,080) | - | $5,572 53,550 kWh |
$278 139 kW-months/year |
$890 - $ |
$(-1,080) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,360 Cost: $4,485 |
$2,862 | 27,450 | $198 | 101 | $300 | - | - | - | $2,862 27,450 kWh |
$198 101 kW-months/year |
$300 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes |