IAC Assessment: AM0802
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0802
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2020
Principal Product Pipe fittings, threaded connectors, and pressure fittings
NAICS 332919 - Other Metal Valve and Pipe Fitting Manufacturing
SIC 3494 - Valves And Pipe Fittings, Nec
Sales $10,000,000-$50,000,000
# of Employees 80
Plant Area (Sq.Ft.) 85,000
Annual Production 522,000 Pieces
Production Hrs. Annual 2,375
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $56,958 739,935 kWh $0.08
Electricity Demand $36,110 5,988 kW-months/year $6.03
Electricity Fees $10,575 - $ -
TOTAL ENERGY COSTS $103,643
RECOMMENDED SAVINGS* $45,053 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $44,513
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$33,740
Cost:
$4,500
- - - - $6,740 - - - $27,000 - -
-
kWh
-
-
kW-months/year
$6,740
-
$
-
-
$
$27,000
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,090
Cost:
$13,250
$2,160 27,000 $950 162 - - $980 - - - $2,160
27,000
kWh
$950
162
kW-months/year
-
-
$
$980
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,146
Cost:
$1,950
$1,200 15,000 $246 42 - - $700 - - - $1,200
15,000
kWh
$246
42
kW-months/year
-
-
$
$700
-
$
-
-
$
04: 2.8123 PAY UTILITY BILLS ON TIME Savings:
$1,850
Cost:
-
- - - - $1,850 - - - - - -
-
kWh
-
-
kW-months/year
$1,850
-
$
-
-
$
-
-
$
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,512
Cost:
$2,280
$1,512 18,900 - - - - - - - - $1,512
18,900
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,175
Cost:
$1,200
$816 10,200 $359 61 - - - - - - $816
10,200
kWh
$359
61
kW-months/year
-
-
$
-
-
$
-
-
$
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$540
Cost:
$25
$375 4,685 $165 28 - - - - - - $375
4,685
kWh
$165
28
kW-months/year
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$45,053
Cost:
$23,205
$6,063 75,785 $1,720 293 $8,590 - $1,680 - $27,000 - $6,063
75,785
kWh
$1,720
293
kW-months/year
$8,590
-
$
$1,680
-
$
$27,000
-
$
TOTAL IMPLEMENTED Savings:
$44,513
Cost:
$23,180
$5,688 71,100 $1,555 265 $8,590 - $1,680 - $27,000 - $5,688
71,100
kWh
$1,555
265
kW-months/year
$8,590
-
$
$1,680
-
$
$27,000
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost