Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2022 |
Principal Product | Sanitized water |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | $5,000,000-$10,000,000 |
# of Employees | 5 |
Plant Area (Sq.Ft.) | 30,000 |
Annual Production | 2,372,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $199,607 | 5,596,357 | kWh | $0.04 |
Electricity Demand | $159,726 | 17,914 | kW-months/year | $8.92 |
Electricity Fees | $4,473 | - | $ | - |
TOTAL ENERGY COSTS | $363,806 | |||
RECOMMENDED SAVINGS* | $22,197 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $22,197 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $12,100 Cost: $11,315 |
- | - | $12,100 | 1,130 | - | - | - | - |
- - kWh |
$12,100 1,130 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $6,240 Cost: $8,070 |
- | - | $6,240 | 623 | - | - | - | - |
- - kWh |
$6,240 623 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,850 Cost: $890 |
$1,510 | 41,900 | $340 | 59 | - | - | - | - |
$1,510 41,900 kWh |
$340 59 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4156 ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM |
Savings: $1,270 Cost: $2,420 |
$900 | 25,030 | - | - | - | - | $370 | - |
$900 25,030 kWh |
- - kW-months/year |
- - MMBtu |
$370 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $570 Cost: $1,820 |
- | - | $250 | 25 | $320 | 8,800 | - | - |
- - kWh |
$250 25 kW-months/year |
$320 8,800 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $167 Cost: $35 |
$110 | 3,075 | $57 | 10 | - | - | - | - |
$110 3,075 kWh |
$57 10 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,197 Cost: $24,550 |
$2,520 | 70,005 | $18,987 | 1,847 | $320 | 8,800 | $370 | - | $2,520 70,005 kWh |
$18,987 1,847 kW-months/year |
$320 8,800 MMBtu |
$370 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $22,197 Cost: $24,550 |
$2,520 | 70,005 | $18,987 | 1,847 | $320 | 8,800 | $370 | - | $2,520 70,005 kWh |
$18,987 1,847 kW-months/year |
$320 8,800 MMBtu |
$370 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |